AI data centers: a census of the campuses
Series 2 · AI campus pipeline · records to 16 Oct 2026
Where capacity for AI training and inference is running, being built or has been announced — 634 campuses, each with its operator, country, status and the capacity its source publishes, counted in megawatts and summed only where a number exists.
Key facts
- As of 16 Oct 2026, Compute Census counts 634 AI data center campuses in 55 countries, 467 of them with a published capacity.
- AI campuses under construction add up to 48.3 GW of published capacity and announced ones to 31.6 GW (records to 16 Oct 2026).
- 24 single AI campuses are rated at 1 GW or more, together 37.6 GW of published capacity (records to 16 Oct 2026).
- United States leads the census with 233 AI campuses and 50.6 GW of published capacity (records to 16 Oct 2026).
- Operational, 271
- Under construction, 249
- Announced, 114
Figure 2.1Published AI campus capacity by status, MW
§1What makes a data center an "AI data center"
There is no certificate for it. An AI data center is a building — usually a campus of several — designed around racks of accelerators instead of racks of general-purpose servers, and three physical properties separate it from a conventional hall: how much power each rack draws, how that heat is removed, and how much power the site can secure from the grid.
Rack density
The unit of AI compute is a server holding eight accelerators, and its power draw sets everything else. NVIDIA rates a single H100 SXM at up to 700 W. An eight-GPU DGX B200 system is specified at about 14.3 kW maximum. Four such systems in one rack would pass 57 kW (our arithmetic, not a vendor figure). At the extreme, NVIDIA's GB200 NVL72 places 72 GPUs and 36 CPUs in a single rack connected by 130 TB/s of NVLink, so the rack itself becomes the computer.
In our records, 24 campuses publish a maximum rack density. Their median is 100 kW per rack and the highest plausible value is 250 kW; 1 record lists a figure above 300 kW that is unlikely to be per rack and is left out of that median. Most operators do not publish the number at all, which is why density is a column in the census table but not a filter for inclusion.
Liquid cooling
Air can carry away only so much heat from a rack before fans, aisle containment and chillers stop keeping up. The newest parts assume liquid. NVIDIA describes the GB200 NVL72 as a rack-scale, liquid-cooled design. The Register reports AMD's MI355X at 1.4 kW per GPU and notes that at that level a liquid-cooling loop is required, while the air-cooled MI350X sibling is held to roughly 1 kW. A building plumbed for direct-to-chip liquid cooling can host these systems; a hall built for air cannot, whatever its megawatt rating.
Of the 634 campuses here, 241 are recorded with liquid cooling, together 32.9 GW of published capacity. For the rest the source either says air or says nothing, so the figure is a floor on liquid-ready capacity, not an estimate of it.
Power at campus scale
The third difference is size. Across the 1,116 operational facilities in our records that are outside this census and publish a capacity, the median is 7 MW; AI campuses are announced in hundreds of megawatts and increasingly in gigawatts. The IEA put global data centre electricity use at 415 TWh in 2024, around 1.5% of world consumption, and projects it to more than double to about 945 TWh by 2030 in its base case. The same report says a typical AI-focused data centre uses as much electricity as 100,000 households, and the largest under construction will use roughly 20 times that.
That is why grid access, not land or buildings, sets the pace. In this census the median campus with a published figure is 66 MW, and 24 campuses are rated at 1 GW or more — 37.6 GW between them, 42% of all published capacity in the census.
Density, cooling and power also explain the GPU price index. A GB200 hour costs $13.25 at the median partly because so few buildings can host a liquid-cooled 72-GPU rack; older air-cooled parts are cheap because almost any hall can run them. See the GPU rental price index.
§2Where the capacity is
The United States dominates: 233 campuses and 50.6 GW of published capacity, 57% of the total. Texas alone accounts for 43 campuses and 14.3 GW, more than any country outside the US. Several of the largest sites sit far from the established data center hubs — Richland Parish in Louisiana, Laramie County in Wyoming, Shackelford County in Texas — which is where campuses of this size found land and grid capacity.
Outside the US, Australia (7.0 GW), India (6.4 GW) and Indonesia (4.7 GW) lead. Taken together, the South, East and Southeast Asian markets in the census add 21.3 GW across 211 campuses. Europe totals 5.9 GW across 98 campuses: many sites, but the median European campus with a published figure is 41 MW, tens of megawatts rather than gigawatts.
Figure 2.2Top 15 countries by published AI campus capacity, MW
Table 2.1AI campuses by country: count, published MW and status
| Country | Campuses | With MW | Published MW | Construction | Announced | Operational |
|---|---|---|---|---|---|---|
| United States | 233 | 151 | 50,568 | 100 | 32 | 101 |
| Australia | 27 | 23 | 7,045 | 5 | 11 | 11 |
| India | 51 | 40 | 6,435 | 26 | 7 | 18 |
| Indonesia | 31 | 29 | 4,717 | 13 | 6 | 12 |
| Malaysia | 26 | 22 | 3,495 | 11 | 8 | 7 |
| Thailand | 18 | 16 | 1,929 | 5 | 10 | 3 |
| Japan | 20 | 18 | 1,848 | 12 | 0 | 8 |
| United Kingdom | 17 | 12 | 1,738 | 7 | 3 | 7 |
| Canada | 18 | 10 | 1,593 | 5 | 2 | 11 |
| Finland | 6 | 6 | 984 | 3 | 0 | 3 |
| Vietnam | 9 | 8 | 920 | 5 | 2 | 2 |
| South Korea | 12 | 11 | 883 | 5 | 2 | 5 |
| Brazil | 6 | 6 | 842 | 5 | 0 | 1 |
| United Arab Emirates | 7 | 7 | 681 | 3 | 2 | 2 |
| Germany | 19 | 15 | 626 | 7 | 8 | 4 |
| Philippines | 10 | 10 | 461 | 3 | 1 | 6 |
| Norway | 5 | 4 | 455 | 1 | 1 | 3 |
| Sweden | 9 | 5 | 450 | 2 | 1 | 6 |
| France | 9 | 6 | 400 | 3 | 2 | 4 |
| Denmark | 4 | 3 | 352 | 1 | 1 | 2 |
| Saudi Arabia | 3 | 3 | 317 | 1 | 2 | 0 |
| Spain | 5 | 5 | 280 | 3 | 2 | 0 |
| Iceland | 4 | 3 | 273 | 0 | 0 | 4 |
| Singapore | 9 | 6 | 268 | 2 | 3 | 4 |
| China | 18 | 4 | 174 | 5 | 0 | 13 |
| Kenya | 3 | 3 | 158 | 0 | 2 | 1 |
| Kazakhstan | 3 | 2 | 150 | 3 | 0 | 0 |
| Turkey | 3 | 3 | 124 | 1 | 1 | 1 |
| Italy | 2 | 2 | 118 | 2 | 0 | 0 |
| Taiwan | 3 | 3 | 107 | 2 | 0 | 1 |
| Egypt | 2 | 2 | 100 | 0 | 2 | 0 |
| New Zealand | 3 | 3 | 98 | 0 | 0 | 3 |
| Hong Kong | 4 | 1 | 71 | 0 | 0 | 4 |
| Bahrain | 2 | 1 | 60 | 1 | 0 | 1 |
| Poland | 2 | 2 | 56 | 0 | 0 | 2 |
| Ireland | 2 | 1 | 52 | 2 | 0 | 0 |
| Qatar | 1 | 1 | 44 | 0 | 1 | 0 |
| Netherlands | 6 | 5 | 36 | 1 | 0 | 5 |
| Peru | 1 | 1 | 20 | 0 | 0 | 1 |
| Estonia | 1 | 1 | 18 | 0 | 0 | 1 |
| Armenia | 2 | 1 | 15 | 0 | 1 | 1 |
| Uzbekistan | 2 | 2 | 14 | 1 | 0 | 1 |
| Nigeria | 2 | 1 | 12 | 0 | 0 | 2 |
| Switzerland | 2 | 2 | 12 | 2 | 0 | 0 |
| Latvia | 2 | 1 | 10 | 0 | 0 | 2 |
| Israel | 1 | 1 | 10 | 0 | 0 | 1 |
| Mexico | 1 | 1 | 8 | 0 | 0 | 1 |
| Jordan | 1 | 1 | 6 | 0 | 0 | 1 |
| Georgia | 1 | 1 | 2 | 1 | 0 | 0 |
| Guyana | 1 | 1 | 1 | 0 | 1 | 0 |
| Greece | 1 | 1 | 1 | 0 | 0 | 1 |
| Tajikistan | 1 | 0 | 0 | 0 | 0 | 1 |
| Colombia | 1 | 0 | 0 | 0 | 0 | 1 |
| Serbia | 1 | 0 | 0 | 0 | 0 | 1 |
| Portugal | 1 | 0 | 0 | 0 | 0 | 1 |
| Total, all countries | 634 | 467 | 89,035 | 249 | 114 | 271 |
MW as published by each campus's source (IT load or grid capacity, as the source states it). Campuses without a published figure count in "Campuses" but not in MW. The total row always covers every country, whatever the filter.
Nothing here matches. Try a shorter search or fewer filters. Clear filters
§3Built, building, announced
Most of the published capacity is not running yet. Campuses under construction add up to 48.3 GW and announced ones to 31.6 GW, against 9.1 GW for operational sites carrying the AI flag. Part of that gap is definitional — operational facilities enter only on the AI flag, while projects in development also enter on size — but it also reflects how recent the build-out is.
Announced capacity deserves the most caution. An announcement is a plan with a number attached; financing, permits and above all grid connections decide whether it becomes a building. The capacity statements below show both directions: regulators approving supply for one campus, a tenant warning of delay at another.
Table 2.2AI campuses by status
| Status | Campuses | With MW | Published MW | Share of MW |
|---|---|---|---|---|
| construction | 249 | 217 | 48,345 | 54.3% |
| announced | 114 | 96 | 31,580 | 35.5% |
| operational | 271 | 154 | 9,111 | 10.2% |
§4The largest campuses
Meta Hyperion (Richland Parish) leads the census at 5,000 MW (construction). OpenAI Project Camellia (Effingham County) follows at 3,210 MW; the Georgia Public Service Commission's approval of 3,200 MW supply for an OpenAI project in Effingham County, listed in the statements below, appears to concern the same site. Of the twenty largest, 15 are in the United States; the rest are in Australia, India and United Kingdom.
Ownership is mixed. Hyperscalers building for themselves (Meta, Google) sit beside developers that lease to AI tenants, companies that started in bitcoin mining (IREN, Galaxy, Hut 8) and GPU clouds building their own campuses (Crusoe, Nebius). Where a source names the tenant, it appears in the operator column.
Table 2.3Twenty largest AI campuses by published capacity
| # | Campus | Operator / tenant | Country | MW | Status |
|---|---|---|---|---|---|
| 1 | Meta Hyperion (Richland Parish)Richland Parish, LA | Meta | United States | 5,000 | construction |
| 2 | OpenAI Project Camellia (Effingham County)Effingham County, GA | OpenAI (developer Octans GA LLC) | United States | 3,210 | announced |
| 3 | Google Project Tembo (Laramie County)Cheyenne, WY | Google (Jupiter Star Holdings, LLC) | United States | 2,700 | announced |
| 4 | Aligned Data Centers Project PhoenixShippingport, Pennsylvania | Aligned Data Centers | United States | 2,000 | construction |
| 5 | Brookfield / NextEra Paducah AI Campus (DOE Paducah Site)Paducah, KY | Brookfield (developer/operator) / NextEra Energy | United States | 1,800 | announced |
| 6 | Galaxy Helios Data Center CampusDickens, TX | Galaxy Digital (tenant: CoreWeave) | United States | 1,630 | construction |
| 7 | IREN Oklahoma CampusOklahoma | IREN | United States | 1,600 | announced |
| 8 | Western Downs Digital Park (Zerra DC)Dalby (Kogan) | Zerra DC | Australia | 1,440 | announced |
| 9 | CDC Wagga Wagga (Gregadoo)Wagga Wagga | CDC Data Centres | Australia | 1,400 | announced |
| 10 | IREN Sweetwater 1Sweetwater, TX | IREN | United States | 1,400 | construction |
| 11 | Vantage Shackelford County Campus (Frontier)Shackelford County, TX | Vantage Data Centers | United States | 1,400 | construction |
| 12 | Colt DCS / RMZ Visakhapatnam Digital CampusVisakhapatnam (Vizag) | Colt Data Centre Services / RMZ | India | 1,250 | announced |
| 13 | Crusoe Abilene AI Campus (Stargate)Abilene, TX | Crusoe | United States | 1,200 | construction |
| 14 | Nebius Highridge Business Park AI FactoryButler Township, Schuylkill County, PA | Nebius | United States | 1,200 | announced |
| 15 | Nebius Independence AI FactoryIndependence, MO | Nebius | United States | 1,200 | construction |
| 16 | EdgeCore Louisa County Data CentersLouisa County, VA | EdgeCore Digital Infrastructure | United States | 1,100 | construction |
| 17 | STACK Stafford Technology Campus (STC)Stafford, VA | STACK Infrastructure | United States | 1,100 | construction |
| 18 | AdaniConneX Navi MumbaiNavi Mumbai | AdaniConneX | India | 1,000 | announced |
| 19 | Crusoe & Lancium Childress AI CampusChildress, TX | Crusoe | United States | 1,000 | construction |
| 20 | CX Technology Campus (Chapelcross)Annan (Chapelcross) | CX Tech | United Kingdom | 1,000 | announced |
§5Public capacity statements
Alongside the facility records, the census keeps a short register of public statements about capacity: approvals, power deals, financings, allocations and delays, each quoted with its own MW figure and source. These are kept apart from the totals because several describe campuses that are already rows above.
The largest single figure is the 8,000 MW single-tenant campus in Pike County, Ohio announced by Nvidia / SB Energy / OpenAI. In the other direction, Oracle warned it may defer rent on the 2.45 GW Project Jupiter campus in Doña Ana County, New Mexico if a stalled gas pipeline delays power. Singapore allocated 200 MW of power on Jurong Island: DC-CFA2, 50 MW each to four operators.
Table 2.4Capacity statements, newest first (updated 2026-10-15)
| Date | Party | Market | Kind | MW | Statement |
|---|---|---|---|---|---|
| 2026-10-14 | DayOne | JohorMalaysia | financing | 1,000 | DayOne upsized its Malaysia syndicated financing to about $7.2B and reported billings above 1GW and bookings of about 2.3GW. |
| 2026-09-24 | Oracle / Stack Infrastructure | Doña Ana County, New MexicoUnited States | delay | 2,450 | Oracle notified Stack Infrastructure it may defer rent on the 2.45 GW Project Jupiter campus under force majeure if a stalled gas pipeline delays power; the pipeline slips to 2027. |
| 2026-09-24 | VIRTUS Data Centres | Buckinghamshire / SloughUnited Kingdom | financing | 78 | 13-bank consortium led by BNP Paribas, Crédit Agricole CIB, Societe Generale and Standard Chartered committed a £2.45B ($3.24B) package, including a £1.2B green capex facility, to fund the 78MW Saunderton campus, further investment at LONDON19 in Slough, and wider European expansion. |
| 2026-09-21 | New Era Energy & Digital / Vistra | TexasUnited States | power | 207 | 20-year power purchase agreement for up to 207 MW with Vistra's Luminant for Phase 1 of the Texas Critical Data Center project (1.4 GW planned). |
| 2026-09-18 | CleanSpark / Meta (Anviranda) | Sandersville, GeorgiaUnited States | financing | 175 | CSDC Finance priced $2.276B of 7.875% senior secured notes to fund a 175 MW Georgia campus leased to a Meta subsidiary. |
| 2026-09-16 | Blockfusion / CoreWeave | Niagara Falls, New YorkUnited States | lease | not stated | Definitive 15-year anchor lease signed with CoreWeave for the hydro-powered Niagara Falls AI campus; capacity of the leased phase not stated in the release. |
| 2026-09-09 | Zankore (Ooredoo-backed) | IndonesiaIndonesia | financing | 100 | $3.1B senior term loan closed to fund 100 MW of Nvidia AI infrastructure in Indonesia, with a stated path toward 1 GW. |
| 2026-09-08 | Government of Singapore (IMDA) | SingaporeSingapore | regulation | 10 | Digital Infrastructure Bill tabled: data centers at or above 10 MW and major cloud providers will need IMDA licenses; a 3 MW energy-efficiency tier applies. |
| 2026-09-03 | Meta | Kuna, IdahoUnited States | live | not stated | Kuna, Idaho campus activated — a $1.2B, 750,000 sq ft facility with closed-loop cooling and 645 MW of new solar to match its load; IT capacity not published. |
| 2026-08-26 | Georgia Public Service Commission / Georgia Power / OpenAI | Effingham County, GeorgiaUnited States | approval | 3,200 | PSC approved a 25-year contract letting Georgia Power supply up to 3,200 MW to an OpenAI data center; OpenAI pays full infrastructure cost and makes up to 1,000 MW of demand flexible. |
| 2026-08-21 | EDB / IMDA (Singapore) | Jurong Island, SingaporeSingapore | allocation | 200 | 200 MW provisionally allocated under DC-CFA2 to Digital Realty, Equinix, Keppel and ST Telemedia (50 MW each), conditional on >50% low-carbon power and liquid cooling, at a new Jurong Island park. |
| 2026-08-14 | CVC DIF / firstcolo | FrankfurtGermany | announcement | 24 | CVC DIF acquired a majority stake in firstcolo, backing a planned 24 MW AI-ready expansion in Frankfurt. |
| 2026-08-13 | Nvidia / SB Energy / OpenAI | Pike County, OhioUnited States | announcement | 8,000 | Nvidia to invest $1.5B in SB Energy and guarantee AI compute for an 8 GW single-tenant campus leased to OpenAI in Pike County, Ohio. |
| 2026-08-07 | DayOne / TNB Power Generation | Sepang, SelangorMalaysia | power | 1,500 | MOU to explore up to 1.5 GW of dedicated on-site generation for DayOne's planned Sepang, Selangor campus. |
MW is the party's own headline number, IT or grid capacity as they state it. Nothing here is estimated. Each statement's document: Sources, capacity statements.
§6The full census
Every campus in the census, sorted by published capacity. Search by name, operator or city, or narrow the list by status, country or region, capacity class and the rule that brought the campus in; the census field above highlights the same selection. Machine-readable copies: JSON (with every source) and CSV. For every data center in the catalogue — not only the AI-oriented ones — the megawattlas.com atlas maps them.
Table 2.5AI data center campus census, all rows
| Campus | Operator / tenant | Country | MW | Status | Liquid | kW/rack | Basis |
|---|---|---|---|---|---|---|---|
| Meta Hyperion (Richland Parish)Richland Parish, LA | Meta | United States | 5,000 | construction | AI flag + ≥50 MW | ||
| OpenAI Project Camellia (Effingham County)Effingham County, GA | OpenAI (developer Octans GA LLC) | United States | 3,210 | announced | AI flag + ≥50 MW | ||
| Google Project Tembo (Laramie County)Cheyenne, WY | Google (Jupiter Star Holdings, LLC) | United States | 2,700 | announced | AI flag + ≥50 MW | ||
| Aligned Data Centers Project PhoenixShippingport, Pennsylvania | Aligned Data Centers | United States | 2,000 | construction | AI flag + ≥50 MW | ||
| Brookfield / NextEra Paducah AI Campus (DOE Paducah Site)Paducah, KY | Brookfield (developer/operator) / NextEra Energy | United States | 1,800 | announced | AI flag + ≥50 MW | ||
| Galaxy Helios Data Center CampusDickens, TX | Galaxy Digital (tenant: CoreWeave) | United States | 1,630 | construction | AI flag + ≥50 MW | ||
| IREN Oklahoma CampusOklahoma | IREN | United States | 1,600 | announced | yes | AI flag + ≥50 MW | |
| Western Downs Digital Park (Zerra DC)Dalby (Kogan) | Zerra DC | Australia | 1,440 | announced | AI flag + ≥50 MW | ||
| CDC Wagga Wagga (Gregadoo)Wagga Wagga | CDC Data Centres | Australia | 1,400 | announced | AI flag + ≥50 MW | ||
| IREN Sweetwater 1Sweetwater, TX | IREN | United States | 1,400 | construction | yes | AI flag + ≥50 MW | |
| Vantage Shackelford County Campus (Frontier)Shackelford County, TX | Vantage Data Centers | United States | 1,400 | construction | yes | AI flag + ≥50 MW | |
| Colt DCS / RMZ Visakhapatnam Digital CampusVisakhapatnam (Vizag) | Colt Data Centre Services / RMZ | India | 1,250 | announced | yes | AI flag + ≥50 MW | |
| Crusoe Abilene AI Campus (Stargate)Abilene, TX | Crusoe | United States | 1,200 | construction | yes | AI flag + ≥50 MW | |
| Nebius Highridge Business Park AI FactoryButler Township, Schuylkill County, PA | Nebius | United States | 1,200 | announced | AI flag + ≥50 MW | ||
| Nebius Independence AI FactoryIndependence, MO | Nebius | United States | 1,200 | construction | yes | AI flag + ≥50 MW | |
| EdgeCore Louisa County Data CentersLouisa County, VA | EdgeCore Digital Infrastructure | United States | 1,100 | construction | yes | AI flag + ≥50 MW | |
| STACK Stafford Technology Campus (STC)Stafford, VA | STACK Infrastructure | United States | 1,100 | construction | ≥50 MW pipeline | ||
| AdaniConneX Navi MumbaiNavi Mumbai | AdaniConneX | India | 1,000 | announced | ≥50 MW pipeline | ||
| Crusoe & Lancium Childress AI CampusChildress, TX | Crusoe | United States | 1,000 | construction | yes | AI flag + ≥50 MW | |
| CX Technology Campus (Chapelcross)Annan (Chapelcross) | CX Tech | United Kingdom | 1,000 | announced | ≥50 MW pipeline | ||
| Hut 8 Beacon Point CampusNueces County, TX | Hut 8 | United States | 1,000 | construction | yes | AI flag + ≥50 MW | |
| HyperVault Future City CampusHyderabad (Telangana Future City) | HyperVault (TCS) | India | 1,000 | announced | yes | AI flag + ≥50 MW | |
| Meta Sturgeon County AI CampusSturgeon County, Alberta | Meta Platforms | Canada | 1,000 | construction | yes | AI flag + ≥50 MW | |
| Meta–BlackRock El Paso AI CampusEl Paso | Meta Platforms / BlackRock | United States | 1,000 | construction | AI flag + ≥50 MW | ||
| Vantage Port Washington Campus (Lighthouse)Port Washington, WI | Vantage Data Centers | United States | 902 | construction | yes | AI flag + ≥50 MW | |
| Crusoe Abilene AI Campus (Microsoft, 900 MW)Abilene, TX | Crusoe | United States | 900 | construction | yes | AI flag + ≥50 MW | |
| IREN Bundey CampusBundey, SA | IREN | Australia | 800 | announced | AI flag + ≥50 MW | ||
| BDx CGK4 (AI Campus 2)Jakarta (Jatiluhur, Purwakarta) | BDx Data Centers (Indosat Ooredoo Hutchison / Lintasarta joint venture) | Indonesia | 640 | construction | yes | AI flag + ≥50 MW | |
| AdaniConneX HyderabadHyderabad | AdaniConneX | India | 600 | construction | ≥50 MW pipeline | ||
| IREN Sweetwater 2Sweetwater, TX | IREN | United States | 600 | announced | yes | AI flag + ≥50 MW | |
| NEXTDC S7 Eastern CreekSydney (Eastern Creek) | NEXTDC | Australia | 550 | announced | ≥50 MW pipeline | ||
| Yondr Dallas Campus (Lancaster)Lancaster, Texas | Yondr Group | United States | 550 | announced | AI flag + ≥50 MW | ||
| Aligned LBB-01 (Project Caprock, Abernathy)Abernathy | Aligned Data Centers | United States | 540 | construction | yes | AI flag + ≥50 MW | |
| CDC Marsden Park CampusSydney (Marsden Park) | CDC Data Centres | Australia | 504 | construction | yes | AI flag + ≥50 MW | |
| Digital Edge CGK CampusJakarta (Bekasi) | Digital Edge | Indonesia | 500 | construction | yes | AI flag + ≥50 MW | |
| IndoData Center BogorBogor | IndoData Center (Salim Group) | Indonesia | 500 | operational | AI flag | ||
| PowerHouse Grand PrairieGrand Prairie | PowerHouse Data Centers | United States | 500 | construction | ≥50 MW pipeline | ||
| SOS Limited Bintan AI Data Center Campus (Galang Batang)Bintan Island (Galang Batang SEZ) | SOS Limited (Future Digital Trading) | Indonesia | 500 | announced | AI flag + ≥50 MW | ||
| STACK DFW02Lancaster, TX | STACK Infrastructure | United States | 500 | construction | AI flag + ≥50 MW | ||
| YTL Green Data Center ParkKulai | YTL Data Center Holdings | Malaysia | 500 | construction | AI flag + ≥50 MW | ||
| EdgeCore Phoenix (Mesa) Data CentersMesa, AZ | EdgeCore Digital Infrastructure | United States | 496 | operational | yes | AI flag | |
| DayOne Kabil Industrial Tech Park (KITP)Batam | DayOne Data Centers | Indonesia | 450 | construction | AI flag + ≥50 MW | ||
| atNorth FIN04 Myllykoski Mega SiteKouvola (Myllykoski) | atNorth | Finland | 430 | construction | yes | AI flag + ≥50 MW | |
| ServerFarm HTX1 HoustonHouston, TX | ServerFarm | United States | 410 | operational | AI flag | ||
| Anthropic / TeraWulf Justified Data Campus (Hawesville)Hawesville, Kentucky | TeraWulf (developer/operator) / Anthropic (tenant) | United States | 401 | construction | AI flag + ≥50 MW | ||
| Ada Infrastructure VA1Virginia (I-95 South corridor) | Ada Infrastructure | United States | 400 | construction | AI flag + ≥50 MW | ||
| Applied Digital Polaris Forge 1 (Ellendale)Ellendale, ND | Applied Digital | United States | 400 | operational | yes | AI flag | |
| CDC Laverton CampusMelbourne (Laverton) | CDC Data Centres | Australia | 400 | construction | AI flag + ≥50 MW | ||
| Prime Data Centers AUS01 (Lockhart Campus)Lockhart, TX | Prime Data Centers | United States | 384 | announced | yes | AI flag + ≥50 MW | |
| NEXTDC S4 Horsley ParkSydney (Horsley Park) | NEXTDC | Australia | 365 | announced | ≥50 MW pipeline | ||
| Compass Red Oak CampusRed Oak, TX | Compass Datacenters | United States | 360 | construction | yes | AI flag + ≥50 MW | |
| CoreWeave Greater Jakarta AI Cloud CampusGreater Jakarta (exact sites not yet disclosed) | CoreWeave | Indonesia | 360 | announced | AI flag + ≥50 MW | ||
| Firmus x Nvidia Batam AI Factory CampusBatam | Firmus Technologies / DayOne | Indonesia | 360 | announced | yes | AI flag + ≥50 MW | |
| Lake Mariner Data CampusBarker, NY | TeraWulf | United States | 360 | construction | AI flag + ≥50 MW | ||
| CDC Brooklyn CampusMelbourne (Brooklyn) | CDC Data Centres | Australia | 350 | operational | AI flag | ||
| Keel Infrastructure (Bitfarms) Panther Creek CampusCarbon County, PA | Keel Infrastructure (Bitfarms) | United States | 350 | construction | yes | AI flag + ≥50 MW | |
| Hut 8 River Bend CampusSt. Francisville, LA | Hut 8 | United States | 330 | construction | yes | AI flag + ≥50 MW | |
| Corscale Gainesville CrossingGainesville | Corscale | United States | 326 | construction | ≥50 MW pipeline | ||
| Cayuga CampusLansing, NY | TeraWulf | United States | 320 | announced | AI flag + ≥50 MW | ||
| Compass Meridian CampusMeridian, MS | Compass Datacenters | United States | 320 | construction | ≥50 MW pipeline | ||
| Nebius Lappeenranta AI FactoryLappeenranta | Nebius | Finland | 310 | construction | yes | AI flag + ≥50 MW | |
| Ada Infrastructure São PauloSão Paulo | Ada Infrastructure | Brazil | 300 | construction | ≥50 MW pipeline | ||
| AirTrunk TOK1 Tokyo EastTokyo (Inzai) | AirTrunk | Japan | 300 | operational | AI flag | ||
| atNorth SWE04 Sollefteå Mega SiteSollefteå (Långsele) | atNorth | Sweden | 300 | announced | yes | 1000 | AI flag + ≥50 MW |
| Bell AI Fabric SaskatchewanRM of Sherwood, near Regina, SK | Bell AI Fabric | Canada | 300 | construction | yes | AI flag + ≥50 MW | |
| Cipher Digital Barber LakeColorado City, TX | Cipher Digital (Cipher Mining) | United States | 300 | construction | yes | AI flag + ≥50 MW | |
| CleanSpark Brazoria County AI CampusBrazoria County, TX | CleanSpark | United States | 300 | announced | yes | AI flag + ≥50 MW | |
| Nebius Vineland AI Data CenterVineland, NJ | Nebius | United States | 300 | construction | yes | AI flag + ≥50 MW | |
| NFD Korea Dangjin AI CampusDangjin | NFD Korea | South Korea | 300 | announced | yes | 160 | AI flag + ≥50 MW |
| Novva MesaMesa | Novva Data Centers | United States | 300 | construction | AI flag + ≥50 MW | ||
| PDG JH2Kulai | Princeton Digital Group | Malaysia | 300 | announced | AI flag + ≥50 MW | ||
| SoftBank Hokkaido Tomakomai AI Data CenterTomakomai | SoftBank Corp. / IDC Frontier | Japan | 300 | construction | AI flag + ≥50 MW | ||
| Soluna Dorothy 3West Texas, TX | Soluna | United States | 300 | announced | AI flag + ≥50 MW | ||
| Stavian Digital ParkHo Chi Minh City | Stavian Hightech Infrastructure | Vietnam | 300 | announced | AI flag + ≥50 MW | ||
| Vantage Johor Campus (former Yondr Sedenak)Kulai | Vantage Data Centers | Malaysia | 300 | operational | yes | AI flag | |
| Ada Infrastructure Tokyo West 2 (TKW2)Tokyo (West) | Ada Infrastructure | Japan | 295 | construction | ≥50 MW pipeline | ||
| BDx CGK5 (AI Campus 3)Jakarta (Karawang, Suryacipta) | BDx Data Centers (Indosat Ooredoo Hutchison / Lintasarta joint venture) | Indonesia | 290 | construction | AI flag + ≥50 MW | ||
| Vantage Ashburn III CampusAshburn | Vantage Data Centers | United States | 288 | construction | ≥50 MW pipeline | ||
| CleanSpark Austin County AI CampusAustin County, TX | CleanSpark | United States | 285 | construction | yes | AI flag + ≥50 MW | |
| AirTrunk JHB3 & JHB4Iskandar Puteri | AirTrunk | Malaysia | 280 | announced | AI flag + ≥50 MW | ||
| AirTrunk JHB2Johor Bahru | AirTrunk | Malaysia | 270 | operational | yes | AI flag | |
| Core Scientific Denton (CoreWeave)Denton, TX | Core Scientific | United States | 260 | operational | yes | AI flag | |
| Vantage Cyberjaya II CampusCyberjaya | Vantage Data Centers | Malaysia | 256 | construction | ≥50 MW pipeline | ||
| AdaniConneX PunePune | AdaniConneX | India | 250 | announced | ≥50 MW pipeline | ||
| atNorth DEN02 Varde Mega SiteVarde | atNorth | Denmark | 250 | announced | yes | AI flag + ≥50 MW | |
| CoreWeave Kenilworth AI Data Center (NEST Campus)Kenilworth, NJ | CoreWeave | United States | 250 | construction | AI flag + ≥50 MW | ||
| Data4 PAR03 (Nozay)Nozay | Data4 | France | 250 | announced | AI flag + ≥50 MW | ||
| STACK PHX02Phoenix (Skyway) | STACK Infrastructure | United States | 250 | construction | AI flag + ≥50 MW | ||
| AirTrunk HYD1Hyderabad | AirTrunk | India | 243 | construction | AI flag + ≥50 MW | ||
| GreenSquareDC MEL1Melbourne (Spotswood) | GreenSquareDC | Australia | 240 | announced | hybrid | ≥50 MW pipeline | |
| Nscale Ward CountyWard County, TX | Nscale | United States | 240 | announced | yes | AI flag + ≥50 MW | |
| PDG JC4Jakarta (Bekasi) | Princeton Digital Group | Indonesia | 240 | construction | AI flag + ≥50 MW | ||
| QTS Richmond 3Sandston (Richmond) | QTS Data Centers | United States | 240 | construction | ≥50 MW pipeline | ||
| Stream DFWC (Wilmer II)Wilmer | Stream Data Centers | United States | 240 | construction | ≥50 MW pipeline | ||
| Stargate Norway (Nscale / Aker, Narvik)Narvik | Nscale / Aker (50/50 joint venture) | Norway | 230 | construction | yes | AI flag + ≥50 MW | |
| Vantage Reno CampusTahoe Reno | Vantage Data Centers | United States | 224 | construction | ≥50 MW pipeline | ||
| Fermi Campus 1 / TensorWave TEX1 (Project Matador)Amarillo, Texas | Fermi America (Fermi Campus 1 LLC) / TensorWave | United States | 222 | construction | yes | AI flag + ≥50 MW | |
| EdgeCore Reno Data CentersReno, NV | EdgeCore Digital Infrastructure | United States | 216 | construction | yes | AI flag + ≥50 MW | |
| Ada Infrastructure DocklandsLondon (Royal Docks) | Ada Infrastructure | United Kingdom | 210 | construction | AI flag + ≥50 MW | ||
| Applied Digital Delta Forge 2Brookwood, Alabama | Applied Digital | United States | 210 | construction | yes | AI flag + ≥50 MW | |
| Stratus Technology RayongRayong | Stratus Technology (ZDATA Technologies) | Thailand | 203 | announced | AI flag + ≥50 MW | ||
| AIMS 200MW AI Data Centre CyberjayaCyberjaya | AIMS Data Centre | Malaysia | 200 | announced | AI flag + ≥50 MW | ||
| Applied Digital Polaris Forge 2 (Harwood)Harwood, ND | Applied Digital | United States | 200 | construction | yes | AI flag + ≥50 MW | |
| CDC Eastern Creek CampusSydney (Eastern Creek) | CDC Data Centres | Australia | 200 | operational | AI flag | ||
| CDC Maddington CampusPerth (Maddington) | CDC Data Centres | Australia | 200 | announced | yes | AI flag + ≥50 MW | |
| Compass Hoffman Estates CampusHoffman Estates, IL | Compass Datacenters | United States | 200 | construction | ≥50 MW pipeline | ||
| DC BLOX Atlanta WestLithia Springs | DC BLOX | United States | 200 | operational | yes | AI flag | |
| EdgeConneX Cyberjaya CampusCyberjaya | EdgeConneX | Malaysia | 200 | announced | 20 | ≥50 MW pipeline | |
| Empyrion MY1 Johor Data Centre CampusIskandar Puteri (Nusajaya, SiLC) | Empyrion Digital | Malaysia | 200 | construction | yes | AI flag + ≥50 MW | |
| Evolution DC TH02 (Samut Prakan)Bangkok (Samut Prakan) | Evolution Data Centres | Thailand | 200 | construction | yes | AI flag + ≥50 MW | |
| Khazna DammamDammam | Khazna Data Centers | Saudi Arabia | 200 | announced | AI flag + ≥50 MW | ||
| LG Uplus Paju Data CenterPaju | LG Uplus | South Korea | 200 | construction | yes | AI flag + ≥50 MW | |
| Microsoft–G42 UAE Datacenter ExpansionAbu Dhabi | Microsoft / G42 | United Arab Emirates | 200 | announced | AI flag + ≥50 MW | ||
| Omnia Pecém Data Center (ByteDance)Pecém (São Gonçalo do Amarante) | Omnia (Pátria Investimentos) | Brazil | 200 | construction | AI flag + ≥50 MW | ||
| PDG JH1Kulai | Princeton Digital Group | Malaysia | 200 | operational | AI flag | ||
| PowerHouse IrvingIrving | PowerHouse Data Centers | United States | 200 | construction | ≥50 MW pipeline | ||
| SGI-HCM CampusHo Chi Minh City (Cu Chi) | Kinh Bac City Development Holding Corporation (KBC) / AIC / VietinBank | Vietnam | 200 | construction | AI flag + ≥50 MW | ||
| Skybox PowerCampus DallasLancaster | Skybox Datacenters | United States | 200 | construction | ≥50 MW pipeline | ||
| Skyline Data Center and Cloud Services ChachoengsaoChachoengsao | Skyline Data Center and Cloud Services Co., Ltd. (DAMAC Group) | Thailand | 200 | announced | yes | AI flag + ≥50 MW | |
| STACK POR03Portland (Hillsboro) | STACK Infrastructure | United States | 200 | construction | AI flag + ≥50 MW | ||
| Stargate UAEAbu Dhabi | OpenAI / Oracle / Khazna (G42) | United Arab Emirates | 200 | construction | AI flag + ≥50 MW | ||
| Tecto TGRU1 (Santana de Parnaíba, under construction)Santana de Parnaíba | Tecto Data Centers | Brazil | 200 | construction | AI flag + ≥50 MW | ||
| TM Nxera Data Centre Campus — Iskandar PuteriIskandar Puteri | TM Nxera (Telekom Malaysia / Nxera-Singtel JV) | Malaysia | 200 | construction | yes | AI flag + ≥50 MW | |
| Zenith Data Center and Cloud ServicesPathum Thani (Navanakorn) | Zenith Data Center and Cloud Services Co., Ltd. | Thailand | 200 | announced | AI flag + ≥50 MW | ||
| EdgeCore Culpeper Data CentersCulpeper | EdgeCore Digital Infrastructure | United States | 196 | announced | yes | AI flag + ≥50 MW | |
| Vantage Fredericksburg Campus (VA4)Fredericksburg, VA | Vantage Data Centers | United States | 192 | construction | ≥50 MW pipeline | ||
| Vantage New Albany CampusNew Albany | Vantage Data Centers | United States | 192 | construction | ≥50 MW pipeline | ||
| Ada Infrastructure Tokyo East 2 (TKE2)Tokyo (East) | Ada Infrastructure | Japan | 190 | construction | ≥50 MW pipeline | ||
| Soluna RosaTexas, TX | Soluna | United States | 187 | announced | AI flag + ≥50 MW | ||
| DayOne Chonburi Tech Park (CTP1)Chonburi | DayOne Data Centers | Thailand | 180 | construction | yes | AI flag + ≥50 MW | |
| DC BLOX Charleston NorthBerkeley County, South Carolina | DC BLOX | United States | 180 | construction | AI flag + ≥50 MW | ||
| QTS Richmond 2Sandston (Richmond) | QTS Data Centers | United States | 180 | construction | ≥50 MW pipeline | ||
| Abernathy HPC Campus (TeraWulf / Fluidstack JV)Abernathy, TX | TeraWulf / Fluidstack | United States | 168 | construction | AI flag + ≥50 MW | ||
| GDS at YTL Green Data Center ParkKulai | GDS Holdings / YTL Power | Malaysia | 168 | announced | ≥50 MW pipeline | ||
| Meta-Reliance AI Data Center JamnagarJamnagar, Gujarat | Reliance Industries (built-to-suit for Meta) | India | 168 | construction | yes | AI flag + ≥50 MW | |
| QTS DenverDenver (Aurora) | QTS Data Centers | United States | 160 | construction | ≥50 MW pipeline | ||
| DC BLOX Atlanta EastConyers | DC BLOX | United States | 154 | construction | AI flag + ≥50 MW | ||
| AdaniConneX NoidaNoida | AdaniConneX | India | 150 | construction | ≥50 MW pipeline | ||
| CtrlS Chonburi CampusChonburi | CtrlS Datacenters | Thailand | 150 | announced | AI flag + ≥50 MW | ||
| Gorilla Technology Korat AI CampusNakhon Ratchasima (Korat) | Gorilla Technology Group | Thailand | 150 | announced | yes | AI flag + ≥50 MW | |
| NEXTDC M4 Port MelbourneMelbourne (Port Melbourne) | NEXTDC | Australia | 150 | announced | ≥50 MW pipeline | ||
| PDG MU1 Navi MumbaiNavi Mumbai (Airoli) | Princeton Digital Group | India | 150 | operational | AI flag | ||
| xAI Colossus 1Memphis, TN | xAI | United States | 150 | operational | yes | AI flag | |
| EDGNEX Data Centers by DAMAC — Jakarta (Cikarang)Jakarta (Cikarang, Bekasi) | EDGNEX Data Centers (DAMAC) | Indonesia | 144 | construction | AI flag + ≥50 MW | ||
| SoftBank Sakai AX Factory AI Data CenterSakai, Osaka | SoftBank Corp. | Japan | 140 | construction | AI flag + ≥50 MW | ||
| Verne — KeflavíkKeflavík | Verne | Iceland | 140 | operational | AI flag | ||
| Viettel Cu Chi Data CenterHo Chi Minh City (Cu Chi) | Viettel | Vietnam | 140 | construction | 60 | AI flag + ≥50 MW | |
| Yotta Chennai Data Center ParkChennai | Yotta Data Services | India | 140 | announced | AI flag + ≥50 MW | ||
| Bridge Data Centres IIO ChonburiChonburi | Bridge Data Centres IIO (Thailand) Co., Ltd. | Thailand | 134 | announced | yes | AI flag + ≥50 MW | |
| AirTrunk MAA1Chennai | AirTrunk | India | 128 | construction | AI flag + ≥50 MW | ||
| STT Fairview 1Metro Manila (Quezon City) | STT GDC Philippines | Philippines | 124 | operational | AI flag | ||
| Sabey Data Centers SDC QuincyQuincy, WA | Sabey Data Centers | United States | 123 | operational | AI flag | ||
| Aligned IAD-02 (Ashburn)Ashburn | Aligned Data Centers | United States | 120 | operational | yes | AI flag | |
| atNorth NOR01 Haugaland Mega SiteTysvær (Haugaland) | atNorth | Norway | 120 | announced | yes | AI flag + ≥50 MW | |
| Novva Data Centers West JordanWest Jordan, UT | Novva Data Centers | United States | 120 | operational | AI flag | ||
| PDG JC3 BekasiJakarta (Bekasi) | Princeton Digital Group | Indonesia | 120 | construction | AI flag + ≥50 MW | ||
| PDG MU2 Navi MumbaiNavi Mumbai | Princeton Digital Group | India | 120 | construction | ≥50 MW pipeline | ||
| PowerHouse ArcolaLeesburg | PowerHouse Data Centers | United States | 120 | construction | yes | AI flag + ≥50 MW | |
| Sabey Data Centers SDC UmatillaUmatilla, OR | Sabey Data Centers | United States | 120 | construction | AI flag + ≥50 MW | ||
| Soluna HedyTexas, TX | Soluna | United States | 120 | announced | AI flag + ≥50 MW | ||
| EdgeCore Ashburn Campus (Sterling)Sterling | EdgeCore Digital Infrastructure | United States | 114 | construction | yes | AI flag + ≥50 MW | |
| Pure Data Centres — Finland (Seinäjoki, SJK01)Seinäjoki | Pure Data Centres Group / SDC Ventures (JV) | Finland | 110 | construction | yes | AI flag + ≥50 MW | |
| Compass El Mirage CampusEl Mirage, AZ | Compass Datacenters | United States | 108 | construction | ≥50 MW pipeline | ||
| ServerFarm ARK1 ClarksvilleClarksville, AR | ServerFarm | United States | 108 | construction | AI flag + ≥50 MW | ||
| PDG Greater Beijing Campus (LF1/LF2)Beijing (Langfang) | Princeton Digital Group | China | 103 | operational | AI flag | ||
| AKASHI Data Center 1Astana | AKASHI Data Center PLC | Kazakhstan | 100 | construction | yes | AI flag + ≥50 MW | |
| Aligned SLC-03 (West Jordan)West Jordan | Aligned Data Centers | United States | 100 | operational | yes | AI flag | |
| Core Scientific Port Muskogee (CoreWeave)Port Muskogee, OK | Core Scientific | United States | 100 | construction | yes | AI flag + ≥50 MW | |
| CoreWeave Lancaster AI Data CenterLancaster, PA | CoreWeave | United States | 100 | announced | yes | AI flag + ≥50 MW | |
| Digital Edge–B.Grimm Chonburi CampusChonburi (Eastern Economic Corridor) | Digital Edge / B.Grimm Power | Thailand | 100 | construction | AI flag + ≥50 MW | ||
| EcoCloud / G42 Olkaria Geothermal Data CenterOlkaria | EcoCloud / G42 | Kenya | 100 | announced | AI flag + ≥50 MW | ||
| GEDC RayongRayong | Gulf Edge | Thailand | 100 | announced | yes | AI flag + ≥50 MW | |
| Khazna Ankara (Başkent OIZ)Ankara | Khazna Data Centers | Turkey | 100 | announced | ≥50 MW pipeline | ||
| Khazna QAJ01Ajman | Khazna Data Centers | United Arab Emirates | 100 | construction | yes | AI flag + ≥50 MW | |
| Moro Hub Green Data Centre (Warsan)Dubai | Moro Hub (Digital DEWA) | United Arab Emirates | 100 | construction | AI flag + ≥50 MW | ||
| Nabiax ADC3 (Alcalá Data Center 3)Alcalá de Henares (Madrid) | Nabiax | Spain | 100 | construction | AI flag + ≥50 MW | ||
| Novva North Las VegasNorth Las Vegas, NV | Novva Data Centers | United States | 100 | operational | AI flag | ||
| Novva Tahoe RenoTahoe Reno, NV | Novva Data Centers | United States | 100 | operational | AI flag | ||
| NTT Bangkok 4Chonburi | NTT Global Data Centers | Thailand | 100 | construction | AI flag + ≥50 MW | ||
| PLDT VITRO Cavite Data CenterGeneral Trias, Cavite | PLDT / VITRO Inc. | Philippines | 100 | announced | AI flag + ≥50 MW | ||
| QTS Hillsboro 3Portland (Hillsboro) | QTS Data Centers | United States | 100 | construction | ≥50 MW pipeline | ||
| SAIGONTEL AI Data Centre Complex (Tân Tập)Tân Tập (Tây Ninh) | SAIGONTEL / World Harmony / SAIF Eagle II consortium | Vietnam | 100 | announced | AI flag + ≥50 MW | ||
| ServerFarm CTX2 HoustonHouston, TX | ServerFarm | United States | 100 | operational | AI flag | ||
| Soluna EllenTexas, TX | Soluna | United States | 100 | announced | AI flag + ≥50 MW | ||
| Soluna Kati 2Southeast Texas, TX | Soluna | United States | 100 | announced | AI flag + ≥50 MW | ||
| VITRO Santa RosaSanta Rosa, Laguna | ePLDT (VITRO Inc.) | Philippines | 100 | operational | AI flag | ||
| Colt DCS Hayes Digital Park ExpansionLondon | Colt DCS | United Kingdom | 97 | announced | AI flag + ≥50 MW | ||
| Colt Chennai Data CentreChennai (Ambattur) | Colt DCS | India | 96 | announced | ≥50 MW pipeline | ||
| NTT Ashburn VA11 Data CenterGainesville | NTT Global Data Centers | United States | 96 | construction | ≥50 MW pipeline | ||
| PDG BT1 BatamBatam | Princeton Digital Group | Indonesia | 96 | construction | ≥50 MW pipeline | ||
| PDG TY1 Saitama (Tokyo)Tokyo (Saitama) | Princeton Digital Group | Japan | 96 | operational | AI flag | ||
| STACK FRA01Liederbach (Frankfurt) | STACK Infrastructure | Germany | 96 | construction | ≥50 MW pipeline | ||
| CtrlS Mumbai Data Center CampusMumbai | CtrlS Datacenters | India | 95 | operational | yes | AI flag | |
| Ascenty Sumaré 3Sumaré | Ascenty (Digital Realty) | Brazil | 90 | construction | yes | AI flag + ≥50 MW | |
| CyrusOne LON6London | CyrusOne | United Kingdom | 90 | construction | ≥50 MW pipeline | ||
| Nscale LoughtonLoughton, Essex | Nscale | United Kingdom | 90 | operational | yes | AI flag | |
| PDG HY1 HyderabadHyderabad | Princeton Digital Group | India | 90 | construction | ≥50 MW pipeline | ||
| QTS San Antonio 2San Antonio | QTS Data Centers | United States | 90 | construction | ≥50 MW pipeline | ||
| Iron Mountain MUM-3Mumbai | Iron Mountain | India | 85 | construction | ≥50 MW pipeline | ||
| NextGen Data Center and Cloud Services (DAMAC Digital)Pathum Thani (Navanakorn) | DAMAC Digital | Thailand | 84 | announced | AI flag + ≥50 MW | ||
| Sabey Data Centers SDC AustinAustin, TX | Sabey Data Centers | United States | 84 | operational | yes | AI flag | |
| atNorth ICE02 Keflavik Mega SiteKeflavík | atNorth | Iceland | 83 | operational | yes | 100 | AI flag |
| CyrusOne FRA7Frankfurt | CyrusOne | Germany | 81 | construction | ≥50 MW pipeline | ||
| Colt Tokyo Yoshikawa Data CentreYoshikawa (Saitama) | Colt DCS | Japan | 80 | construction | yes | AI flag + ≥50 MW | |
| Corscale KincoraSterling | Corscale | United States | 80 | construction | ≥50 MW pipeline | ||
| EcoDataCenter 1 — FalunFalun | EcoDataCenter | Sweden | 80 | operational | AI flag | ||
| IREN Mackenzie CampusMackenzie, BC | IREN | Canada | 80 | operational | AI flag | ||
| Kemet Data Center (Intro Group)Ain Sokhna | Intro Group | Egypt | 80 | announced | ≥50 MW pipeline | ||
| Keppel/DDSP Taiwan DC CampusGuishan, Taoyuan | Keppel Data Centre Fund II / DDSP | Taiwan | 80 | construction | ≥50 MW pipeline | ||
| National AI Computing Center (Haenam)Haenam, Jeollanam-do (Solasido Data Center Park) | Korea AI Computing Center (KOACC) — Samsung SDS-led consortium | South Korea | 80 | construction | AI flag + ≥50 MW | ||
| NEXTDC S3 SydneySydney (Artarmon) | NEXTDC | Australia | 80 | operational | AI flag | ||
| NEXTDC S5 Macquarie ParkSydney (Macquarie Park) | NEXTDC | Australia | 80 | announced | ≥50 MW pipeline | ||
| Vistas Technology Amata City ChonburiChonburi | Vistas Technology (ZDATA Technologies) | Thailand | 80 | announced | AI flag + ≥50 MW | ||
| Green Mountain OSL-EnebakkOslo (Enebakk) | Green Mountain | Norway | 75 | operational | AI flag | ||
| maincubes FRA05Frankfurt | maincubes | Germany | 75 | announced | ≥50 MW pipeline | ||
| Soluna AnnieTexas, TX | Soluna | United States | 75 | announced | AI flag + ≥50 MW | ||
| CtrlS Chennai Data Center ParkChennai | CtrlS Datacenters | India | 72 | operational | yes | 70 | AI flag |
| EdgeCore Silicon Valley Data CentersSanta Clara, CA | EdgeCore Digital Infrastructure | United States | 72 | operational | AI flag | ||
| PDG CH1 ChennaiChennai | Princeton Digital Group | India | 72 | construction | AI flag + ≥50 MW | ||
| Prime Data Centers ORD01-01Elk Grove Village | Prime Data Centers | United States | 72 | operational | yes | AI flag | |
| Pure Data Centres — London Park RoyalLondon | Pure Data Centres Group / SEGRO (JV) | United Kingdom | 72 | announced | yes | AI flag + ≥50 MW | |
| STACK COP02Copenhagen | STACK Infrastructure | Denmark | 72 | construction | ≥50 MW pipeline | ||
| STACK KIX01Keihanna (Kyoto Prefecture) | STACK Infrastructure | Japan | 72 | construction | ≥50 MW pipeline | ||
| Yondr / Cerberus Manassas Data CenterManassas, Virginia | Yondr Group / Cerberus Capital Management | United States | 72 | announced | AI flag + ≥50 MW | ||
| Global Switch Hong KongHong Kong (Tseung Kwan O) | Global Switch | Hong Kong | 71 | operational | yes | AI flag | |
| AirTrunk SGP2Singapore | AirTrunk | Singapore | 70 | construction | ≥50 MW pipeline | ||
| EdgeConneX Bukit JalilKuala Lumpur | EdgeConneX | Malaysia | 70 | construction | 20 | AI flag + ≥50 MW | |
| Pure Data Centres — London Brent Cross, Building 2 (LON01)London | Pure Data Centres Group | United Kingdom | 70 | construction | ≥50 MW pipeline | ||
| Pure Data Centres — Madrid (Meco, MAD01)Meco | Pure Data Centres Group | Spain | 70 | construction | ≥50 MW pipeline | ||
| QTS East Windsor 1East Windsor | QTS Data Centers | United States | 70 | construction | ≥50 MW pipeline | ||
| Verne — The AirVantaa | Verne | Finland | 70 | operational | AI flag | ||
| Vantage Osaka Campus (KIX1)Osaka (Ibaraki) | Vantage Data Centers | Japan | 68 | construction | ≥50 MW pipeline | ||
| Ada Infrastructure Tokyo East 1 (TKE1)Tokyo (East) | Ada Infrastructure | Japan | 67 | construction | ≥50 MW pipeline | ||
| Skybox Atlantic StationPlano | Skybox Datacenters | United States | 66 | construction | yes | AI flag + ≥50 MW | |
| Bitdeer AI A202 (Johor Campus)Johor Bahru | Bitdeer AI (Bitdeer Technologies Group) | Malaysia | 65 | announced | yes | AI flag + ≥50 MW | |
| NEXTDC KL1Kuala Lumpur | NEXTDC | Malaysia | 65 | operational | AI flag | ||
| Vantage Milan I Campus (MXP1)Milan (Melegnano) | Vantage Data Centers | Italy | 64 | construction | ≥50 MW pipeline | ||
| Vantage Santa Clara III Campus (CA3)Santa Clara | Vantage Data Centers | United States | 64 | construction | ≥50 MW pipeline | ||
| Colt Frankfurt 4 & 5 Data CentresWiesbaden (Frankfurt area) | Colt DCS | Germany | 63 | announced | ≥50 MW pipeline | ||
| STT Palava 4Mumbai (Palava) | ST Telemedia Global Data Centres (India) | India | 61 | construction | AI flag + ≥50 MW | ||
| STT Palava 5Mumbai (Palava) | ST Telemedia Global Data Centres (India) | India | 61 | construction | AI flag + ≥50 MW | ||
| Aligned IAD-01 (Ashburn)Ashburn | Aligned Data Centers | United States | 60 | operational | yes | AI flag | |
| Bitdeer AI A103 (Cyberjaya Campus)Cyberjaya | Bitdeer AI (Bitdeer Technologies Group) | Malaysia | 60 | announced | yes | AI flag + ≥50 MW | |
| Digital Edge SEL3Incheon | Digital Edge | South Korea | 60 | construction | AI flag + ≥50 MW | ||
| Element Critical Houston TwoKaty, TX | Element Critical | United States | 60 | construction | yes | AI flag + ≥50 MW | |
| Epoch Digital Nusajaya Tech Park (Project Mercury)Johor Bahru (Nusajaya) | Epoch Digital (Actis) | Malaysia | 60 | construction | AI flag + ≥50 MW | ||
| Iron Mountain RCH-3Sandston (Richmond) | Iron Mountain | United States | 60 | construction | ≥50 MW pipeline | ||
| Iron Mountain RCH-4Sandston (Richmond) | Iron Mountain | United States | 60 | construction | ≥50 MW pipeline | ||
| Pi Amaravati Data CenterVijayawada (Mangalagiri) | Pi Data Centers | India | 60 | construction | AI flag + ≥50 MW | ||
| STACK NAL01New Albany | STACK Infrastructure | United States | 60 | construction | AI flag + ≥50 MW | ||
| stc/center3 Data Center Park — Al QurainAl Qurain | stc Bahrain / center3 | Bahrain | 60 | construction | AI flag + ≥50 MW | ||
| STT Jakarta 7Cikarang, Bekasi (STT Jakarta campus) | STT GDC Indonesia | Indonesia | 60 | announced | ≥50 MW pipeline | ||
| STT Jakarta 8Cikarang, Bekasi (STT Jakarta campus) | STT GDC Indonesia | Indonesia | 60 | announced | ≥50 MW pipeline | ||
| STT Jakarta 9Cikarang, Bekasi (STT Jakarta campus) | STT GDC Indonesia | Indonesia | 60 | announced | ≥50 MW pipeline | ||
| STT VNG Ho Chi Minh City 2Ho Chi Minh City (Tan Thuan) | STT GDC – VNG joint venture | Vietnam | 60 | construction | AI flag + ≥50 MW | ||
| Viettel An Khánh Data CenterHanoi (Hoài Đức) | Viettel | Vietnam | 60 | construction | AI flag + ≥50 MW | ||
| Desert Dragon Al-Kharj Hyperscaler Data Center #1 (KHS-1)Al-Kharj | Desert Dragon Data Centers | Saudi Arabia | 59 | construction | yes | AI flag + ≥50 MW | |
| Nxera DC TuasSingapore (Tuas) | Nxera | Singapore | 58 | operational | yes | AI flag | |
| Pure Data Centres — Riyadh (RUH01)Riyadh | Pure Data Centres Group / Dune Vaults (JV) | Saudi Arabia | 58 | announced | ≥50 MW pipeline | ||
| STACK TOR01Toronto | STACK Infrastructure | Canada | 56 | operational | AI flag | ||
| Vantage Berlin I Campus (BER1)Berlin (Ludwigsfelde) | Vantage Data Centers | Germany | 56 | construction | ≥50 MW pipeline | ||
| Vantage Frankfurt II Campus (FRA2)Frankfurt (Raunheim) | Vantage Data Centers | Germany | 56 | construction | ≥50 MW pipeline | ||
| CapitaLand Data Centre Navi Mumbai Tower 2Navi Mumbai | CapitaLand India Trust | India | 55 | construction | yes | AI flag + ≥50 MW | |
| Colt Paris 5 & 6 Data CentresLes Ulis | Colt DCS | France | 55 | announced | yes | AI flag + ≥50 MW | |
| CDC Hobsonville Campus TwoAuckland (Hobsonville) | CDC Data Centres | New Zealand | 54 | operational | AI flag | ||
| Colt Berlin 1 & 2 Data CentresBerlin | Colt DCS | Germany | 54 | announced | ≥50 MW pipeline | ||
| CyrusOne MIL2Milan | CyrusOne | Italy | 54 | construction | ≥50 MW pipeline | ||
| Prime Data Centers ORD01-02Elk Grove Village | Prime Data Centers | United States | 54 | announced | yes | AI flag + ≥50 MW | |
| Prime Data Centers ORD01-03Elk Grove Village | Prime Data Centers | United States | 54 | announced | yes | AI flag + ≥50 MW | |
| iXAfrica NBOX2 (Tilisi)Limuru (Tilisi) | IXAfrica Data Centres | Kenya | 53 | announced | yes | AI flag + ≥50 MW | |
| NTT Noida 2 Data CenterNoida | NTT Global Data Centers | India | 53 | construction | ≥50 MW pipeline | ||
| Vantage Dublin Campus (DUB1)Dublin | Vantage Data Centers | Ireland | 52 | construction | ≥50 MW pipeline | ||
| Csquare DFW1Fort Worth | Csquare | United States | 52 | operational | AI flag | ||
| CDC Hume Campus TwoCanberra (Hume) | CDC Data Centres | Australia | 51 | operational | AI flag | ||
| Pi DC1Cyberjaya | Pi Data Centre (PiDC Holdings / Jakel Group) | Malaysia | 51 | construction | ≥50 MW pipeline | ||
| ACS/Iridium Alcalá de Henares Data CenterAlcalá de Henares (Madrid area) | ACS Group (Iridium) | Spain | 50 | announced | ≥50 MW pipeline | ||
| Ada Infrastructure Rio de JaneiroRio de Janeiro | Ada Infrastructure | Brazil | 50 | construction | ≥50 MW pipeline | ||
| Anant Raj Cloud PanchkulaPanchkula | Anant Raj Cloud (Ashok Cloud) | India | 50 | construction | ≥50 MW pipeline | ||
| atNorth ICE03 Akureyri Mega SiteAkureyri | atNorth | Iceland | 50 | operational | yes | 100 | AI flag |
| Data Center Valley (Ekibastuz)Ekibastuz | KT-Telecom (Kazakhtelecom) with Firebird | Kazakhstan | 50 | construction | yes | AI flag + ≥50 MW | |
| Digital Realty Jurong Island (DC-CFA2)Singapore (Jurong Island) | Digital Realty | Singapore | 50 | announced | ≥50 MW pipeline | ||
| IREN Prince George CampusPrince George, BC | IREN | Canada | 50 | operational | AI flag | ||
| Keppel Data Centre Singapore 11 (Keppel DC SGP 11)Singapore (Jurong Island) | Keppel Data Centres | Singapore | 50 | announced | yes | AI flag + ≥50 MW | |
| KT Cloud Cheongna AI Data CenterIncheon (Cheongna) | KT Cloud | South Korea | 50 | announced | yes | AI flag + ≥50 MW | |
| NeutraDC Nxera BatamBatam | NeutraDC (Telkom Indonesia) / Nxera | Indonesia | 50 | construction | yes | ≥50 MW pipeline | |
| STT Palava 1Mumbai (Palava) | ST Telemedia Global Data Centres (India) | India | 50 | construction | AI flag + ≥50 MW | ||
| Techno Digital ChennaiChennai | Techno Digital (Techno Electric) | India | 50 | operational | AI flag | ||
| PDG SE1 IncheonIncheon | Princeton Digital Group | South Korea | 48 | construction | AI flag | ||
| Prime Data Centers PHX01-01Avondale, AZ | Prime Data Centers | United States | 48 | construction | yes | AI flag | |
| Prime Data Centers PHX01-02Avondale, AZ | Prime Data Centers | United States | 48 | construction | yes | AI flag | |
| Macquarie IC3 Super WestSydney (Macquarie Park) | Macquarie Data Centres | Australia | 47 | construction | yes | AI flag | |
| Naver GAK SejongSejong | Naver Cloud | South Korea | 47 | operational | AI flag | ||
| CDC Fyshwick CampusCanberra (Fyshwick) | CDC Data Centres | Australia | 45 | operational | AI flag | ||
| STT GDC India Chennai Siruseri CampusChennai | STT GDC India | India | 45 | operational | AI flag | ||
| Colovore DFW01Mesquite | Colovore | United States | 45 | construction | yes | AI flag | |
| MEEZA M-Vault 6-8 ExpansionDoha | MEEZA | Qatar | 44 | announced | AI flag | ||
| PDG NJ1 NanjingNanjing | Princeton Digital Group | China | 43 | operational | AI flag | ||
| Sify Rabale Data Center Campus (Tower 5)Navi Mumbai | Sify Technologies | India | 43 | operational | yes | 130 | AI flag |
| Beyond.pl Data Center 2Poznań | Beyond.pl | Poland | 42 | operational | yes | 140 | AI flag |
| DayOne Kodaira Data CenterTokyo (Kodaira) | DayOne | Japan | 42 | construction | AI flag | ||
| atNorth FIN02 Helsinki Metro Site (Espoo)Helsinki (Espoo) | atNorth | Finland | 40 | operational | yes | 100 | AI flag |
| Colovore AUS01Hutto | Colovore | United States | 40 | construction | yes | AI flag | |
| Colt Paris 2 Data CentreVillebon-sur-Yvette | Colt DCS | France | 40 | construction | yes | AI flag | |
| Element Critical Houston OneKaty, TX | Element Critical | United States | 40 | operational | yes | AI flag | |
| Gwangmyeong AI Data Center PohangPohang | Private investment consortium / Hyundai Engineering & Construction | South Korea | 40 | construction | AI flag | ||
| maincubes FRA04Dietzenbach (Frankfurt area) | maincubes | Germany | 40 | announced | yes | AI flag | |
| Novva Colorado SpringsColorado Springs | Novva Data Centers | United States | 40 | operational | AI flag | ||
| Prime Data Centers MAD01-01Alcobendas (Madrid) | Prime Data Centers | Spain | 40 | announced | yes | AI flag | |
| STACK CHI01Elk Grove Village | STACK Infrastructure | United States | 40 | operational | AI flag | ||
| STT Jakarta 5Cikarang, Bekasi (STT Jakarta campus) | STT GDC Indonesia | Indonesia | 40 | construction | AI flag | ||
| STT Jakarta 6Cikarang, Bekasi (STT Jakarta campus) | STT GDC Indonesia | Indonesia | 40 | construction | AI flag | ||
| WhiteFiber NC-1Madison (North Carolina) | WhiteFiber | United States | 40 | construction | yes | 150 | AI flag |
| CDC Beard CampusCanberra (Beard) | CDC Data Centres | Australia | 39 | construction | AI flag | ||
| Aligned DFW-02 (Plano)Plano | Aligned Data Centers | United States | 36 | operational | yes | AI flag | |
| Aligned ORD-02 (Northlake)Northlake | Aligned Data Centers | United States | 36 | operational | yes | AI flag | |
| Cologix COL7Johnstown, OH | Cologix | United States | 36 | construction | AI flag | ||
| DCI Indonesia JK6Jakarta (Cibitung) | DCI Indonesia | Indonesia | 36 | operational | yes | AI flag | |
| Digital Edge SEL2Incheon | Digital Edge | South Korea | 36 | operational | yes | 130 | AI flag |
| H5 Data Centers ChicagoChicago | H5 Data Centers | United States | 36 | operational | AI flag | ||
| Novva South San FranciscoSouth San Francisco | Novva Data Centers | United States | 36 | construction | yes | AI flag | |
| NTT Ashburn VA7 Data CenterAshburn | NTT Global Data Centers | United States | 36 | construction | AI flag | ||
| NTT Osaka OSK12 Data CenterOsaka (Ibaraki) | NTT Global Data Centers | Japan | 36 | construction | yes | AI flag | |
| STACK CHI02Elk Grove Village | STACK Infrastructure | United States | 36 | construction | AI flag | ||
| MC Digital Realty NRT12Tokyo | MC Digital Realty | Japan | 34 | operational | yes | AI flag | |
| Kao Data Manchester (Stockport)Stockport | Kao Data | United Kingdom | 33 | construction | AI flag | ||
| Prime Data Centers LAX01-01Los Angeles | Prime Data Centers | United States | 33 | operational | yes | AI flag | |
| Colt DCS Frankfurt 3 Data CentreFrankfurt | Colt DCS | Germany | 32 | construction | AI flag | ||
| Colovore DFW02Fort Worth | Colovore | United States | 32 | construction | yes | AI flag | |
| Colt Paris 3 Data CentreVillebon-sur-Yvette | Colt DCS | France | 32 | construction | yes | AI flag | |
| NTT Chicago CH3 Data CenterItasca | NTT Global Data Centers | United States | 32 | construction | AI flag | ||
| STT Fairview 2Metro Manila (Quezon City) | STT GDC Philippines | Philippines | 32 | construction | AI flag | ||
| STT Fairview 3Metro Manila (Quezon City) | STT GDC Philippines | Philippines | 32 | construction | AI flag | ||
| STT Fairview 4Metro Manila (Quezon City) | STT GDC Philippines | Philippines | 32 | construction | AI flag | ||
| Khazna AUH6 Masdar CityAbu Dhabi | Khazna Data Centers | United Arab Emirates | 32 | operational | AI flag | ||
| Colt DCS London 5 Data CentreLondon (Hayes) | Colt DCS | United Kingdom | 32 | construction | AI flag | ||
| Ada Infrastructure Tokyo West 1 (TKW1)Tokyo (West) | Ada Infrastructure | Japan | 31 | operational | AI flag | ||
| Aligned DFW-01 (Plano)Plano | Aligned Data Centers | United States | 30 | operational | yes | AI flag | |
| atNorth DEN01 Copenhagen Metro SiteBallerup (Copenhagen) | atNorth | Denmark | 30 | operational | yes | 100 | AI flag |
| atNorth SWE02 Stockholm Metro Site (Akalla)Stockholm (Akalla) | atNorth | Sweden | 30 | construction | yes | 100 | AI flag |
| CMC Hyperscale DC SHTPHo Chi Minh City | CMC Corporation | Vietnam | 30 | construction | AI flag | ||
| eStruxture MTL-2Montreal | eStruxture | Canada | 30 | operational | AI flag | ||
| IREN Canal Flats CampusCanal Flats, BC | IREN | Canada | 30 | operational | AI flag | ||
| L&T-Cloudfiniti SPD1Sriperumbudur | L&T Cloudfiniti (Larsen & Toubro) | India | 30 | operational | yes | AI flag | |
| Nscale GlomfjordGlomfjord | Nscale | Norway | 30 | operational | AI flag | ||
| NTT Keihanna OSK11 Data CenterSeika (Kyoto Prefecture) | NTT Global Data Centers | Japan | 30 | operational | AI flag | ||
| Techno Digital NoidaNoida | Techno Digital (Techno Electric) | India | 30 | construction | AI flag | ||
| Viettel Hoa Lac Data CenterHanoi (Hoa Lac) | Viettel IDC | Vietnam | 30 | operational | AI flag | ||
| Yotta D1Greater Noida | Yotta Data Services | India | 30 | operational | AI flag | ||
| VOLT UAE / DIEZ AI Data Centre (Dubai Silicon Oasis)Dubai | VOLT UAE (JV with DIEZ) | United Arab Emirates | 29 | announced | yes | AI flag | |
| Cloud Carrier DB1Moss Vale | Cloud Carrier | Australia | 28 | operational | yes | 140 | AI flag |
| Conapto STHLM 4 SouthStockholm | Conapto | Sweden | 28 | operational | yes | AI flag | |
| eStruxture CAL-2Balzac, AB | eStruxture | Canada | 26 | operational | AI flag | ||
| MC Digital Realty NRT14Tokyo | MC Digital Realty | Japan | 25 | operational | yes | AI flag | |
| 123NET DC1 (Southfield)Southfield | 123NET | United States | 24 | operational | yes | AI flag | |
| firstcolo FRA7Rosbach vor der Höhe | firstcolo | Germany | 24 | announced | yes | AI flag | |
| Lambda Kansas City AI FactoryKansas City, MO | Lambda | United States | 24 | construction | yes | AI flag | |
| MC Digital Realty KIX15Osaka (Ibaraki) | MC Digital Realty | Japan | 24 | construction | yes | AI flag | |
| STT Jakarta 2Jakarta (Cikarang) | ST Telemedia Global Data Centres (STT GDC) | Indonesia | 24 | operational | AI flag | ||
| STT Jakarta 2Cikarang, Bekasi (STT Jakarta campus) | STT GDC Indonesia | Indonesia | 24 | operational | yes | AI flag | |
| STT Jakarta 3Cikarang, Bekasi (STT Jakarta campus) | STT GDC Indonesia | Indonesia | 24 | construction | yes | AI flag | |
| STT Pune 5Pune (Dighi) | ST Telemedia Global Data Centres (India) | India | 24 | operational | AI flag | ||
| Telia Helsinki Data Center (HDC)Helsinki | Telia Finland | Finland | 24 | operational | AI flag | ||
| Iron Mountain CHN-1Chennai | Iron Mountain | India | 23 | construction | yes | AI flag | |
| Digital Edge EDGE2Jakarta (Kuningan Mulia, South Jakarta) | Digital Edge | Indonesia | 23 | operational | yes | AI flag | |
| ETIX Bangkok 2 (BKK2)Samut Prakan | ETIX Everywhere / Interlink Telecom | Thailand | 23 | construction | AI flag | ||
| CDC Hobsonville Campus OneAuckland (Hobsonville) | CDC Data Centres | New Zealand | 22 | operational | AI flag | ||
| CDC Silverdale Campus OneAuckland (Silverdale) | CDC Data Centres | New Zealand | 22 | operational | AI flag | ||
| ServerFarm TiTAN Moses LakeMoses Lake, WA | ServerFarm | United States | 22 | operational | AI flag | ||
| CDC Hume Campus OneCanberra (Hume) | CDC Data Centres | Australia | 21 | operational | AI flag | ||
| 5C Data Centers PHX01Phoenix | 5C Data Centers | United States | 20 | construction | yes | AI flag | |
| Africa Data Centers Egypt (announced)Cairo | Africa Data Centers (Cassava Technologies) / Vodafone Business | Egypt | 20 | announced | AI flag | ||
| Chief Telecom LY2Neihu, Taipei | Chief Telecom | Taiwan | 20 | operational | yes | 150 | AI flag |
| Cirion Lima (LIM2)Lima | Cirion Technologies | Peru | 20 | operational | AI flag | ||
| DayOne SG1 (Jalan Buroh)Singapore | DayOne Data Centres | Singapore | 20 | construction | yes | AI flag | |
| ENKA Tuzla Data Center-01Istanbul (Tuzla) | ENKA Data Solutions | Turkey | 20 | construction | AI flag | ||
| Equinix SG6Singapore | Equinix | Singapore | 20 | announced | yes | AI flag | |
| GSA01 Bangkok Campus (Bang Phli)Samut Prakan | GSA Data Center (Gulf, Singtel Nxera, AIS) | Thailand | 20 | operational | yes | AI flag | |
| Kuaishou Intelligent Cloud Ulanqab Data Center No.2Ulanqab | Kuaishou Intelligent Cloud | China | 20 | operational | AI flag | ||
| OpCore PAR5Saint-Ouen-l'Aumône | OpCore | France | 20 | operational | AI flag | ||
| Prime Data Centers FRA01-01Frankfurt | Prime Data Centers | Germany | 20 | announced | yes | AI flag | |
| Prime Data Centers SJC01San Jose | Prime Data Centers | United States | 20 | operational | yes | AI flag | |
| Pure Data Centres — Abu Dhabi (Yas Island, AUH01)Abu Dhabi | Pure Data Centres Group | United Arab Emirates | 20 | operational | yes | AI flag | |
| Pure Data Centres — Jakarta (Bekasi, JKT01)Bekasi | Pure Data Centres Group | Indonesia | 20 | operational | AI flag | ||
| Quetta QTT-MAD1Tres Cantos | Quetta Data Centers | Spain | 20 | construction | yes | AI flag | |
| Telstra InfraCo Clayton Data CentreMelbourne (Clayton) | Telstra InfraCo | Australia | 20 | operational | AI flag | ||
| Telstra InfraCo St Leonards Data CentreSydney (St Leonards) | Telstra InfraCo | Australia | 20 | operational | AI flag | ||
| Iron Mountain CHN-2Chennai | Iron Mountain | India | 19 | construction | yes | AI flag | |
| DCI Indonesia E1Jakarta (Kuningan, South Jakarta) | DCI Indonesia | Indonesia | 18 | operational | AI flag | ||
| Greenergy Data CentersHarku (Tallinn area) | Greenergy Data Centers | Estonia | 18 | operational | yes | AI flag | |
| Prime Data Centers SMF01-02Sacramento | Prime Data Centers | United States | 18 | construction | yes | AI flag | |
| SDC Manhattan (Intergate.Manhattan)New York | Sabey Data Centers | United States | 18 | operational | AI flag | ||
| Telehouse Tokyo Tama 5-2ndTokyo | Telehouse (KDDI) | Japan | 18 | construction | yes | AI flag | |
| Kao Data Harlow CampusHarlow | Kao Data | United Kingdom | 18 | operational | AI flag | ||
| FutureData Park, first data center (Global Telecommunications Group)Kuching | FutureData Sdn Bhd (TSG Group / Cyclect) | Malaysia | 17 | construction | yes | AI flag | |
| Colovore ORD02West Chicago | Colovore | United States | 16 | construction | yes | AI flag | |
| Colovore ORD03Aurora | Colovore | United States | 16 | construction | yes | AI flag | |
| Colovore ORD04Aurora | Colovore | United States | 16 | construction | yes | AI flag | |
| Colovore RNO01Sparks | Colovore | United States | 16 | operational | yes | AI flag | |
| Colovore RNO02Reno | Colovore | United States | 16 | construction | yes | AI flag | |
| maincubes FRA03Schwalbach (Frankfurt area) | maincubes | Germany | 16 | operational | yes | AI flag | |
| STT Johor 1Iskandar Puteri (Johor) | STT GDC Malaysia (joint venture with Basis Bay) | Malaysia | 16 | construction | AI flag | ||
| BDx Indonesia CGK3AJakarta (South Jakarta) | BDx Data Centers | Indonesia | 15 | operational | yes | AI flag | |
| Csquare LHR3Reading | Csquare | United Kingdom | 15 | operational | yes | AI flag | |
| DUG McCloud Data Centre (Skybox Houston)Houston | DUG Technology | United States | 15 | operational | yes | AI flag | |
| Firebird DC-1Hrazdan | Firebird | Armenia | 15 | operational | yes | AI flag | |
| GreenSquareDC SYD1Sydney (Norwest) | GreenSquareDC | Australia | 15 | construction | AI flag | ||
| Atman WAW-3Warsaw (Duchnice) | Atman | Poland | 14 | operational | AI flag | ||
| Sify Hyderabad Data CenterHyderabad | Sify Technologies | India | 14 | operational | yes | 130 | AI flag |
| ServerFarm TOR1 TorontoToronto | ServerFarm | Canada | 14 | operational | AI flag | ||
| Switch Datacenters AMS4Diemen | Switch Datacenters | Netherlands | 14 | operational | AI flag | ||
| ePLDT VITRO Makati 2Makati City, Metro Manila | ePLDT (VITRO Inc.) | Philippines | 12 | operational | AI flag | ||
| AIMS Cyberjaya Block 3Cyberjaya | AIMS Data Centre | Malaysia | 12 | operational | AI flag | ||
| atNorth SWE01 Stockholm Metro Site (Kista)Stockholm (Kista) | atNorth | Sweden | 12 | operational | yes | 100 | AI flag |
| Converge ICT Angeles Data CenterAngeles City, Pampanga | Converge ICT Solutions Inc. | Philippines | 12 | operational | AI flag | ||
| DataVolt TAS-1Tashkent | DataVolt | Uzbekistan | 12 | construction | yes | AI flag | |
| Digital Realty ICN10 (Digital Seoul 1)Seoul | Digital Realty | South Korea | 12 | operational | AI flag | ||
| NTT Jakarta 2 Annex (JKT2A)Jakarta | NTT DATA (Global Data Centers) | Indonesia | 12 | construction | AI flag | ||
| Rack Centre LGS2Lagos | Rack Centre | Nigeria | 12 | operational | AI flag | ||
| ServerFarm LON1 London (Feltham)Feltham, London | ServerFarm | United Kingdom | 11 | operational | AI flag | ||
| Delska EU North Riga LV DC1Riga | Delska | Latvia | 10 | operational | yes | 250 | AI flag |
| Digital Edge NARRA1Greater Manila (Biñan, Laguna) | Digital Edge | Philippines | 10 | operational | yes | 5 | AI flag |
| KINX GwacheonGwacheon | KINX | South Korea | 10 | operational | AI flag | ||
| Prime Data Centers SJC06San Jose | Prime Data Centers | United States | 10 | operational | yes | AI flag | |
| ServerFarm ISR1 Tel AvivNorth Tel Aviv | ServerFarm | Israel | 10 | operational | AI flag | ||
| Prime Data Centers SJC02San Jose | Prime Data Centers | United States | 9 | construction | yes | AI flag | |
| Prime Data Centers SJC03San Jose | Prime Data Centers | United States | 9 | announced | yes | AI flag | |
| Prime Data Centers SJC04San Jose | Prime Data Centers | United States | 9 | announced | yes | AI flag | |
| Switch Datacenters AMS3Amsterdam | Switch Datacenters | Netherlands | 9 | operational | AI flag | ||
| BDx CGK1Jakarta (Central Jakarta) | BDx Data Centers (Indosat Ooredoo Hutchison / Lintasarta joint venture) | Indonesia | 8 | operational | AI flag | ||
| CtrlS Noida Data CenterNoida | CtrlS Datacenters | India | 8 | operational | yes | AI flag | |
| Energy Vault Snyder AI Campus (Crusoe Spark)Snyder, Texas | Energy Vault / Crusoe Cloud | United States | 8 | construction | yes | AI flag | |
| Penta Infra AMS01Haarlem | Penta Infra | Netherlands | 8 | construction | AI flag | ||
| Prime Data Centers SMF01-01Sacramento | Prime Data Centers | United States | 8 | operational | yes | AI flag | |
| TERRANOVA San Miguel de AllendeSan Miguel de Allende, Guanajuato | TERRANOVA (Actis) | Mexico | 8 | operational | AI flag | ||
| Chindata-Dongyangguang Yidu Advanced Computing CampusYidu (Yichang) | Chindata Group | China | 8 | construction | AI flag | ||
| NorthC Münchenstein (Basel) 3Arlesheim (Basel area) | NorthC | Switzerland | 8 | construction | yes | AI flag | |
| Bell AI Fabric Kamloops 1Kamloops | Bell AI Fabric | Canada | 7 | operational | AI flag | ||
| Empyrion Digital TW1Neihu, Taipei | Empyrion Digital | Taiwan | 7 | construction | yes | AI flag | |
| Digital Halo MNL1Cainta, Rizal | Digital Halo | Philippines | 7 | operational | AI flag | ||
| 35D South Beach Mega Data CenterAqaba | 35D (Aqaba Digital Hub) | Jordan | 6 | operational | AI flag | ||
| Colovore ORD01Aurora | Colovore | United States | 6 | operational | yes | AI flag | |
| Colovore SJC01Santa Clara | Colovore | United States | 6 | operational | yes | AI flag | |
| Colovore SJC02Santa Clara | Colovore | United States | 6 | operational | yes | 250 | AI flag |
| Iron Mountain MUM-2Mumbai | Iron Mountain | India | 6 | operational | AI flag | ||
| STT Jaipur 1Jaipur (Sitapura) | ST Telemedia Global Data Centres (India) | India | 6 | operational | AI flag | ||
| STT Kolkata 2Kolkata (New Town) | ST Telemedia Global Data Centres (India) | India | 6 | construction | AI flag | ||
| Portus Data Centers MUC2Kirchheim bei München, near Munich | Portus Data Centers (Portus Data Centers Muenchen GmbH) | Germany | 6 | construction | yes | AI flag | |
| Open DC D8-1Bukit Kayu Hitam, Kedah | Open DC | Malaysia | 5 | operational | AI flag | ||
| PROEN OTT DCBangkok | PROEN Corp | Thailand | 5 | operational | AI flag | ||
| IXAfrica NBOX1Nairobi | IXAfrica Data Centres | Kenya | 5 | operational | AI flag | ||
| NorthC GenevaMeyrin (Geneva area) | NorthC | Switzerland | 5 | construction | yes | AI flag | |
| AtlasEdge Leverkusen (LEV002)Leverkusen | AtlasEdge | Germany | 4 | construction | yes | AI flag | |
| nLighten Amsterdam II (AMS2)Amsterdam (Schiphol-Rijk) | nLighten | Netherlands | 4 | operational | yes | AI flag | |
| DAMAC Digital IZM-01İzmir (Gaziemir) | DAMAC Digital (Red Haven Veri Merkezi A.Ş.) | Turkey | 4 | operational | AI flag | ||
| US Signal IL02 (Aurora)Aurora | US Signal | United States | 4 | construction | AI flag | ||
| LightEdge Minneapolis IChaska, MN | LightEdge | United States | 4 | operational | AI flag | ||
| BDx CGK2Jakarta (South Tangerang) | BDx Data Centers (Indosat Ooredoo Hutchison / Lintasarta joint venture) | Indonesia | 3 | operational | AI flag | ||
| ETIX Lille #4Fretin | ETIX Everywhere | France | 3 | operational | AI flag | ||
| Pi Data Centers Central MumbaiMumbai | Pi Data Centers | India | 3 | construction | AI flag | ||
| nLighten FrankfurtEschborn | nLighten | Germany | 2 | operational | AI flag | ||
| Aligned SP-04 (Osasco)Osasco | Aligned Data Centers | Brazil | 2 | operational | yes | AI flag | |
| Silk Cloud Tbilisi Data CenterTbilisi | Silk Cloud (Silknet) | Georgia | 2 | construction | AI flag | ||
| Soluna GraceTexas, TX | Soluna | United States | 2 | operational | AI flag | ||
| Uztelecom Cloud Hub Tashkent 1Tashkent | Uzbektelecom (UzCloud) | Uzbekistan | 2 | operational | AI flag | ||
| Georgetown Colocation Facility (GuyTech)Georgetown | GuyTech Data Infrastructure Inc. | Guyana | 1 | announced | AI flag | ||
| Switch Datacenters AMS2Woerden | Switch Datacenters | Netherlands | 1 | operational | AI flag | ||
| Synapsecom Athens Data CenterAno Liosia (Athens area) | Synapsecom | Greece | 1 | operational | yes | AI flag | |
| 5C Data Centers - CMH01Columbus | 5C Data Centers | United States | n/p | operational | AI flag | ||
| Aligned ATL-01 (Lithia Springs)Atlanta (Lithia Springs) | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned CMH-02 (Conesville)Conesville | Aligned Data Centers | United States | n/p | construction | yes | AI flag | |
| Aligned DFW-03 (Mansfield)Mansfield | Aligned Data Centers | United States | n/p | construction | yes | AI flag | |
| Aligned DFW-04 (Plano)Plano | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned IAD-03 (Sterling)Sterling | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned IAD-04 (Frederick, MD)Frederick | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned NEO-01 (Sandusky)Sandusky | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned ORD-01 (Northlake)Northlake | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned ORD-03 (Elk Grove Village)Elk Grove Village | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned PDX-01 (Hillsboro)Portland (Hillsboro) | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned Phoenix Campus (PHX-01/02/03)Phoenix | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned PHX-04 (Chandler)Phoenix (Chandler) | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned PHX-06 (Chandler)Phoenix (Chandler) | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned Salt Lake City Campus (SLC-01/02/03/04)Salt Lake City | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned SLC-01 (West Jordan)West Jordan | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned SLC-02 (West Jordan)West Jordan | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Aligned SLC-04 (West Valley City)West Valley City | Aligned Data Centers | United States | n/p | operational | yes | AI flag | |
| Ark Alliance Park (Ealing)London | Ark Data Centres | United Kingdom | n/p | construction | yes | AI flag | |
| Ark Longcross Park (Chertsey)Chertsey | Ark Data Centres | United Kingdom | n/p | operational | yes | AI flag | |
| Ark Union Park (Hayes)London | Ark Data Centres | United Kingdom | n/p | construction | yes | AI flag | |
| Aventus LakesMilwaukee | Aventus Data Centers | United States | n/p | operational | AI flag | ||
| AWS Bharat Future City Data CenterHyderabad (Bharat Future City) | Amazon Web Services (AWS) | India | n/p | construction | AI flag | ||
| AWS Project Rainier (New Carlisle)New Carlisle, IN | Amazon Web Services | United States | n/p | operational | yes | AI flag | |
| Baidu Cloud Computing (Dingxing) CenterDingxing County, Baoding, Hebei | Baidu AI Cloud | China | n/p | operational | AI flag | ||
| Baidu Cloud Computing (Xushui-Dawangdian) CenterXushui District, Baoding, Hebei | Baidu AI Cloud | China | n/p | operational | AI flag | ||
| Baidu Cloud Computing (Yangquan) CenterYangquan, Shanxi | Baidu AI Cloud | China | n/p | operational | AI flag | ||
| Batelco White Space Data CentreHamala | Batelco (Beyon) | Bahrain | n/p | operational | AI flag | ||
| BDx CGK3 - Jakarta TBSJakarta | BDx DC Services | Indonesia | n/p | operational | AI flag | ||
| Bell AI Fabric Kamloops 2 (Thompson Rivers University)Kamloops | Bell AI Fabric | Canada | n/p | construction | AI flag | ||
| Bell AI Fabric MerrittMerritt, BC | Bell AI Fabric | Canada | n/p | announced | AI flag | ||
| Borealis Data Center — Blönduós CampusBlönduós | Borealis Data Center | Iceland | n/p | operational | yes | AI flag | |
| Bulk Infrastructure N01 Data Center CampusKristiansand | Bulk Infrastructure | Norway | n/p | operational | AI flag | ||
| ByteDance Taihang Computing Center (Volcano Cloud)Datong (Guangling) | ByteDance / Volcano Engine | China | n/p | construction | AI flag | ||
| China Mobile Global Intelligence CenterFo Tan, Sha Tin | China Mobile | Hong Kong | n/p | operational | AI flag | ||
| China Telecom Global AI Data CenterHong Kong | China Telecom Global | Hong Kong | n/p | operational | AI flag | ||
| CloudBurst San Marcos Data Center ISan Marcos (Texas) | CloudBurst Data Centers | United States | n/p | construction | yes | AI flag | |
| Core Scientific Auburn 1Auburn, AL | Core Scientific | United States | n/p | operational | AI flag | ||
| Core Scientific Austin 1Austin, TX | Core Scientific | United States | n/p | operational | AI flag | ||
| Core Scientific Calvert City 1-3Calvert City, KY | Core Scientific | United States | n/p | operational | AI flag | ||
| Core Scientific Cottonwood 1 & 2Pecos, TX | Core Scientific | United States | n/p | operational | AI flag | ||
| Core Scientific Dalton 1 & 2Dalton, GA | Core Scientific | United States | n/p | operational | AI flag | ||
| Core Scientific Dalton 3Dalton, GA | Core Scientific | United States | n/p | operational | AI flag | ||
| Core Scientific Grand Forks 1Grand Forks, ND | Core Scientific | United States | n/p | operational | AI flag | ||
| Core Scientific Marble 1Marble, NC | Core Scientific | United States | n/p | operational | AI flag | ||
| CoreSite SV9Santa Clara | CoreSite | United States | n/p | operational | AI flag | ||
| Crusoe AI Campus (Blue Energy, Calhoun County)Calhoun County, TX | Crusoe | United States | n/p | announced | yes | AI flag | |
| darya.ai NVIDIA H200 GPU ClusterDushanbe | darya.ai Ltd | Tajikistan | n/p | operational | AI flag | ||
| Digital Edge BOM1Navi Mumbai | Digital Edge | India | n/p | operational | AI flag | ||
| DUG Kuala Lumpur Data CentreKuala Lumpur | DUG Technology | Malaysia | n/p | operational | yes | AI flag | |
| DUG Perth Data CentrePerth | DUG Technology | Australia | n/p | operational | yes | AI flag | |
| Echelon DUB30 (Kish)Arklow | Echelon Data Centres | Ireland | n/p | construction | AI flag | ||
| EcoDataCenter 2 — BorlängeBorlänge | EcoDataCenter | Sweden | n/p | construction | AI flag | ||
| Envision Galaxy CampusUlanqab, Inner Mongolia | Envision Group | China | n/p | operational | AI flag | ||
| Equinix CH5Elk Grove Village | Equinix | United States | n/p | operational | yes | AI flag | |
| Equinix CH7Westmont | Equinix | United States | n/p | operational | AI flag | ||
| Equinix CN1Chennai | Equinix | India | n/p | operational | AI flag | ||
| Equinix DA11Dallas | Equinix | United States | n/p | operational | AI flag | ||
| Equinix DA2Dallas | Equinix | United States | n/p | operational | AI flag | ||
| Equinix DA3Dallas | Equinix | United States | n/p | operational | AI flag | ||
| Equinix DA6Dallas | Equinix | United States | n/p | operational | AI flag | ||
| Equinix DA9Irving | Equinix | United States | n/p | operational | AI flag | ||
| Equinix DC16Ashburn | Equinix | United States | n/p | operational | yes | AI flag | |
| Equinix DC21Ashburn | Equinix | United States | n/p | operational | AI flag | ||
| Equinix FR2Frankfurt | Equinix | Germany | n/p | operational | yes | AI flag | |
| Equinix HK6Hong Kong (Tsuen Wan) | Equinix | Hong Kong | n/p | operational | yes | AI flag | |
| Equinix JH2Iskandar Puteri | Equinix | Malaysia | n/p | construction | yes | AI flag | |
| Equinix JK1Jakarta | Equinix | Indonesia | n/p | operational | AI flag | ||
| Equinix KL2Kuala Lumpur | Equinix | Malaysia | n/p | announced | AI flag | ||
| Equinix LD5Slough | Equinix | United Kingdom | n/p | operational | yes | AI flag | |
| Equinix MB3Mumbai | Equinix | India | n/p | operational | yes | AI flag | |
| Equinix NY13Elmsford | Equinix | United States | n/p | operational | AI flag | ||
| Equinix NY3Secaucus | Equinix | United States | n/p | operational | AI flag | ||
| Equinix NY4Secaucus | Equinix | United States | n/p | operational | AI flag | ||
| Equinix NY5Secaucus | Equinix | United States | n/p | operational | AI flag | ||
| Equinix NY7North Bergen | Equinix | United States | n/p | operational | AI flag | ||
| Equinix PA10Paris | Equinix | France | n/p | operational | yes | 6 | AI flag |
| Equinix SK1Stockholm | Equinix | Sweden | n/p | operational | AI flag | ||
| Equinix SK2Stockholm | Equinix | Sweden | n/p | operational | AI flag | ||
| Equinix SK3Stockholm | Equinix | Sweden | n/p | operational | AI flag | ||
| Equinix SV11San Jose | Equinix | United States | n/p | operational | AI flag | ||
| Equinix SV15Santa Clara | Equinix | United States | n/p | operational | AI flag | ||
| Equinix SV2Santa Clara | Equinix | United States | n/p | operational | AI flag | ||
| Equinix SV3San Jose | Equinix | United States | n/p | operational | AI flag | ||
| Equinix SY5Sydney (Alexandria) | Equinix | Australia | n/p | operational | yes | AI flag | |
| eStruxture CAL-3Rocky View County, AB | eStruxture | Canada | n/p | construction | AI flag | ||
| eStruxture VAN-3Burnaby, BC | eStruxture | Canada | n/p | operational | AI flag | ||
| Firebird DC-2Hrazdan | Firebird | Armenia | n/p | announced | yes | AI flag | |
| Firmus AI Factory Stirling North (Project Southgate)Stirling North | Firmus Technologies | Australia | n/p | announced | AI flag | ||
| Firmus AI Factory Tailem Bend (Project Southgate)Tailem Bend | Firmus Technologies | Australia | n/p | announced | AI flag | ||
| Fluidstack Cameron County CampusRio Hondo, TX | Fluidstack | United States | n/p | construction | AI flag | ||
| FPT Fornix HCM02Ho Chi Minh City | FPT | Vietnam | n/p | operational | AI flag | ||
| Global Switch AmsterdamAmsterdam | Global Switch | Netherlands | n/p | operational | yes | AI flag | |
| Google AI Hub VisakhapatnamVisakhapatnam (Vizag) | Google / AdaniConneX / Airtel | India | n/p | announced | AI flag | ||
| Google Armstrong CountyArmstrong County, TX | United States | n/p | announced | AI flag | |||
| Google Berkeley CountyBerkeley County, SC | United States | n/p | operational | AI flag | |||
| Google Cedar RapidsCedar Rapids, IA | United States | n/p | announced | AI flag | |||
| Google Chesterfield CountyChesterfield County, VA | United States | n/p | announced | AI flag | |||
| Google Council BluffsCouncil Bluffs, IA | United States | n/p | operational | AI flag | |||
| Google Elmina Data CenterShah Alam (Elmina) | Malaysia | n/p | construction | yes | AI flag | ||
| Google Fort WayneFort Wayne, IN | United States | n/p | operational | AI flag | |||
| Google Haskell CountyHaskell County, TX | United States | n/p | announced | AI flag | |||
| Google HendersonHenderson, NV | United States | n/p | operational | AI flag | |||
| Google Jackson CountyJackson County, AL | United States | n/p | operational | AI flag | |||
| Google LenoirLenoir, NC | United States | n/p | operational | AI flag | |||
| Google LincolnLincoln, NE | United States | n/p | operational | AI flag | |||
| Google MesaMesa, AZ | United States | n/p | operational | AI flag | |||
| Google OmahaOmaha, NE | United States | n/p | operational | AI flag | |||
| Google PapillionPapillion, NE | United States | n/p | operational | AI flag | |||
| Google Pryor (Mayes County)Pryor, OK | United States | n/p | operational | AI flag | |||
| Google StillwaterStillwater, OK | United States | n/p | announced | AI flag | |||
| Google West MemphisWest Memphis, AR | United States | n/p | announced | AI flag | |||
| Google Wilbarger CountyWilbarger County, TX | United States | n/p | construction | AI flag | |||
| GSA02 Chonburi CampusChonburi | GSA Data Center (Gulf, Singtel Nxera, AIS) | Thailand | n/p | announced | yes | AI flag | |
| Huawei Cloud Data Center, Gui'an New AreaGui'an New Area, Guiyang, Guizhou | Huawei Cloud | China | n/p | operational | AI flag | ||
| Huawei Cloud East China (Wuhu) Data Center, Sanshan Plot Phase 1Sanshan Economic and Technological Development Zone, Wuhu, Anhui | Huawei Cloud | China | n/p | operational | yes | AI flag | |
| Hyper Cloud Data CenterAlmaty | Beeline Kazakhstan (VEON) | Kazakhstan | n/p | construction | AI flag | ||
| IONOS Frankfurt Cloud Data CentreFrankfurt | IONOS | Germany | n/p | operational | AI flag | ||
| IREN Childress Campus (Horizon 1-4)Childress, TX | IREN | United States | n/p | construction | yes | AI flag | |
| Kasi Cloud LOS1 (Lekki)Lagos (Lekki) | Kasi Cloud Datacenters | Nigeria | n/p | operational | AI flag | ||
| Kauri CAB Digital Infrastructure — KarbenKarben | Kauri CAB Digital Infrastructure | Germany | n/p | announced | AI flag | ||
| KCDI HochheimHochheim am Main | Kauri CAB Digital Infrastructure (KCDI) | Germany | n/p | announced | AI flag | ||
| KDDI Osaka Sakai Data CenterSakai, Osaka | KDDI | Japan | n/p | operational | hybrid | AI flag | |
| Keppel DC Singapore 7Singapore | Keppel DC REIT | Singapore | n/p | operational | AI flag | ||
| Keppel DC Singapore 8Singapore | Keppel DC REIT | Singapore | n/p | operational | AI flag | ||
| Kolo DK5 CopenhagenCopenhagen (Nordvest) | Kolo | Denmark | n/p | operational | yes | AI flag | |
| Kuaishou Intelligent Cloud Ulanqab Data Center No.1Ulanqab | Kuaishou Intelligent Cloud | China | n/p | operational | AI flag | ||
| Kunming Artificial Intelligence Computing CenterKunming | Yunnan Cloud Above Cloud Big Data Industry Development Co., Ltd. | China | n/p | operational | AI flag | ||
| Meta Tulsa AI Data CenterTulsa | Meta Platforms | United States | n/p | construction | yes | AI flag | |
| Microsoft Azure India South Central Region — HyderabadHyderabad, Telangana | Microsoft | India | n/p | operational | AI flag | ||
| Microsoft Fairwater (Mount Pleasant)Mount Pleasant, WI | Microsoft | United States | n/p | operational | yes | AI flag | |
| Monserrate Data CenterBogotá | Grupo ASD SAS | Colombia | n/p | operational | AI flag | ||
| Nexcenter Osaka 7 Data CenterIbaraki, Osaka | NTT Communications (NTT DOCOMO BUSINESS) — Nexcenter | Japan | n/p | operational | yes | AI flag | |
| NHN Cloud Gwangju National AI Data CenterGwangju | NHN Cloud | South Korea | n/p | operational | AI flag | ||
| nLighten Paris PAR1Lognes | nLighten | France | n/p | operational | AI flag | ||
| Orion Telekom Data Center BelgradeBelgrade | Orion Telekom | Serbia | n/p | operational | AI flag | ||
| Penta Infra PAR01Lognes | Penta Infra | France | n/p | construction | yes | AI flag | |
| PHX15Phoenix (Chandler) | Digital Realty | United States | n/p | operational | AI flag | ||
| PowerHouse CharlotteCharlotte | PowerHouse Data Centers | United States | n/p | construction | AI flag | ||
| RackBank CEN1 (Raipur)Raipur | RackBank | India | n/p | construction | yes | AI flag | |
| RackBank CEN2 (Indore)Indore | RackBank | India | n/p | construction | yes | AI flag | |
| RackBank WST1 (Navi Mumbai)Navi Mumbai | RackBank | India | n/p | construction | yes | AI flag | |
| Related Digital Saline Township AI Campus ("The Barn", Stargate)Saline Township, MI | Related Digital | United States | n/p | construction | yes | AI flag | |
| Riot Platforms Rockdale FacilityRockdale, TX | Riot Platforms | United States | n/p | operational | yes | AI flag | |
| SB Energy Milam County (Stargate/OpenAI)Milam County, TX | SB Energy (SoftBank) | United States | n/p | construction | yes | AI flag | |
| SINES Data Campus (Start Campus)Sines | Start Campus (tenant: Nscale) | Portugal | n/p | operational | yes | AI flag | |
| ST Engineering Cadence DCSingapore (Changi South) | ST Engineering | Singapore | n/p | operational | yes | AI flag | |
| STACK Infrastructure Santa Teresa (Stargate/Oracle)Santa Teresa, NM | STACK Infrastructure | United States | n/p | announced | yes | AI flag | |
| Stream Data Centers PHXAGoodyear, AZ | Stream Data Centers | United States | n/p | operational | AI flag | ||
| TELUS 150 West Georgia AI Data CentreVancouver (Downtown) | TELUS | Canada | n/p | announced | yes | AI flag | |
| TELUS Kamloops Data Centre (AI Factory)Kamloops | TELUS | Canada | n/p | operational | AI flag | ||
| TELUS M3 AI Data Centre (Mount Pleasant, Vancouver)Vancouver (Mount Pleasant) | TELUS | Canada | n/p | construction | yes | AI flag | |
| TELUS Rimouski Data Centre (Sovereign AI Factory)Rimouski | TELUS | Canada | n/p | operational | AI flag | ||
| Tencent Guangdong-Hong Kong-Macao Greater Bay Area Smart Computing CenterZhenjiang District, Shaoguan, Guangdong | Tencent Cloud | China | n/p | construction | yes | AI flag | |
| Tencent Yangtze River Delta AI Advanced Computing CenterSongjiang District, Shanghai | Tencent Cloud | China | n/p | construction | AI flag | ||
| Tet DC7Salaspils | Tet | Latvia | n/p | operational | yes | AI flag | |
| TierPoint Fort WorthFort Worth | TierPoint | United States | n/p | operational | AI flag | ||
| TierPoint St. Louis (Locust St.)St. Louis | TierPoint | United States | n/p | construction | AI flag | ||
| TierPoint TekParkBreinigsville | TierPoint | United States | n/p | operational | AI flag | ||
| True IDC East Bangna CampusBangkok | True IDC | Thailand | n/p | operational | AI flag | ||
| Vantage CWL1 Cardiff CampusCardiff | Vantage Data Centers | United Kingdom | n/p | operational | 125 | AI flag | |
| VNET (21Vianet) Gu'an IDC CampusLangfang (Gu'an) | VNET Group | China | n/p | construction | yes | AI flag | |
| VNET Huailai Super AIDC NodeZhangjiakou (Huailai) | VNET Group | China | n/p | operational | AI flag | ||
| VNET Ulanqab Green G-watt AIDC Flagship BaseUlanqab, Inner Mongolia | VNET Group | China | n/p | operational | AI flag | ||
| xAI MACROHARDRR (Southaven)Southaven, MS | xAI | United States | n/p | construction | AI flag | ||
| Yotta NM1Navi Mumbai | Yotta Data Services | India | n/p | operational | AI flag | ||
| Yotta NM2Navi Mumbai | Yotta Data Services | India | n/p | construction | AI flag |
n/p = capacity not published by the source. Liquid = liquid cooling recorded for the site. kW/rack = maximum density where published. Drawn from 6,018 facility records; 4 duplicate records removed (see methodology). The source of every row is listed under Sources, campus records.
Nothing here matches. Try a shorter search or fewer filters. Clear filters
§7What this census does not show
- Capacity that nobody has published. Many operators disclose a campus but not its megawatts; 167 of the 634 campuses here have no figure, so every total is a lower bound.
- GPU counts. Few campuses publish how many accelerators they hold, and we do not convert megawatts to GPUs.
- Timing. "Under construction" means work has started according to the source; it is not a delivery date.
- Like-for-like megawatts. Some sources quote IT load, others grid connection; the census keeps the number as published and does not normalise it.
Own land near a substation that could host a campus like these? Parcels and developer requests are handled on megawattacres.com.
Sources: the documents behind the explainer, the statements and every campus row are listed on Sources.
Equipping an AI campus?
If you are filling a hall with accelerators or servers, send the model, quantity and site — we return supplier pricing and lead times for purchase or rental.